Given the activities of a project; their optimistic (to), most likely (tm) and pessimistic (tp) time estimates; and their immediate predecessors shown below: a. When is the earliest project completion? b. Which activities are critical (should not be delayed)? (Please have mercy please answer the two questions above. Thank you!)
Contingency Table
A contingency table can be defined as the visual representation of the relationship between two or more categorical variables that can be evaluated and registered. It is a categorical version of the scatterplot, which is used to investigate the linear relationship between two variables. A contingency table is indeed a type of frequency distribution table that displays two variables at the same time.
Binomial Distribution
Binomial is an algebraic expression of the sum or the difference of two terms. Before knowing about binomial distribution, we must know about the binomial theorem.
Given the activities of a project; their optimistic (to), most likely (tm) and pessimistic (tp) time estimates; and their immediate predecessors shown below:
a. When is the earliest project completion?
b. Which activities are critical (should not be delayed)?
(Please have mercy please answer the two questions above. Thank you!)
Step by step
Solved in 3 steps with 4 images