Given is a CPM project network diagram as shown below. Start A с B D E F G H End Start A B C D E F G H End Activity days 0 2 6 8 3 4 2 3 2 0 a) The Project Completion time Blank 1 days. b) The Earliest Start time, ES, of Activity G = Blank 2 days. c) The Latest Finish time, LF, of Activity C = Blank 3 days. d) The critical activities are = Blank 4 (ex. Fill in the answer as: ABCD)
Given is a CPM project network diagram as shown below. Start A с B D E F G H End Start A B C D E F G H End Activity days 0 2 6 8 3 4 2 3 2 0 a) The Project Completion time Blank 1 days. b) The Earliest Start time, ES, of Activity G = Blank 2 days. c) The Latest Finish time, LF, of Activity C = Blank 3 days. d) The critical activities are = Blank 4 (ex. Fill in the answer as: ABCD)
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 21P
Related questions
Question

Transcribed Image Text:Given is a CPM project network diagram as shown below.
Start
A
с
B
D
E
F
G
H
End
Start
A
B
C
D
E
F
G
H
End
Activity
days
0
2
6
8
3
4
2
3
2
0
a) The Project Completion time Blank 1 days.
b) The Earliest Start time, ES, of Activity G = Blank 2 days.
c) The Latest Finish time, LF, of Activity C = Blank 3 days.
d) The critical activities are = Blank 4 (ex. Fill in the answer as: ABCD)
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,