Gibco Service has budgeted the following time-and-material for 2019: Budgeted Costs For 2019 Time Material Charges Charges Painters' wages and benefits $54,000 Service manager's salary and benefits $44,000 Office employee's salary and benefits 7,400 6,000 Cost of paint 50,000 Overhead (supplies, utilities, etc.) 14,000 22,000 Gibco budgets 2,000 hours of paint time in 2019 and will charge a profit of $8 per hour on the labour rate, in addition to a 12% mark-up on the cost of paint. On February 15, 2019, Gibco is asked to prepare a price estimate to paint a building. Gibco estimates that this job will take 25 labour hours and $900 in paint. 1.Calculate the material loading charge rate % for 2019 2. What is the planned profit for the year? Do not enter $ or commas.
Master Budget
A master budget can be defined as an estimation of the revenue earned or expenses incurred over a specified period of time in the future and it is generally prepared on a periodic basis which can be either monthly, quarterly, half-yearly, or annually. It helps a business, an organization, or even an individual to manage the money effectively. A budget also helps in monitoring the performance of the people in the organization and helps in better decision-making.
Sales Budget and Selling
A budget is a financial plan designed by an undertaking for a definite period in future which acts as a major contributor towards enhancing the financial success of the business undertaking. The budget generally takes into account both current and future income and expenses.
Gibco Service has budgeted the following time-and-material for 2019:
Budgeted Costs For 2019 |
||||
|
Time |
Material |
||
|
|
Charges |
Charges |
|
|
Painters' wages and benefits |
$54,000 |
|
|
|
|
|
$44,000 |
|
|
Office employee's salary and benefits |
7,400 |
6,000 |
|
|
Cost of paint |
|
50,000 |
|
|
|
14,000 |
22,000 |
|
|
|
|
|
|
Gibco budgets 2,000 hours of paint time in 2019 and will charge a profit of $8 per hour on the labour rate, in addition to a 12% mark-up on the cost of paint.
On February 15, 2019, Gibco is asked to prepare a price estimate to paint a building. Gibco estimates that this job will take 25 labour hours and $900 in paint.
1.Calculate the material loading charge rate % for 2019
2. What is the planned profit for the year? Do not enter $ or commas.
Step by step
Solved in 2 steps with 2 images