GANTT CHART 1 2 3 Mon 1/6/25 Add tasks with dat Task Mode Actual Actual Task Name Duration Start Start Finish ▼Finish Predecessors Successors Preconstruction 1 day? NA Mon 1/6/25 NA Define Project scope 5 days NA Mon 1/6/25 NA Mon 1/6/25 Fri 1/10/25 and Objectives Assemble Project Team 7 days NA Mon 1/6/25 NA Tue 1/14/25 ㄢ Conduct Site Surveys 10 days NA Mon 1/6/25 NA Fri 1/17/25 and Studies 5 Perform Environmental 1 day? NA Mon 1/6/25 NA Mon 1/6/25 Assessments 6 Submit Plans for 1 day? NA Mon 1/6/25 NA Mon 1/6/25 Permits 7 Obtain Permits 1 day? NA Mon 1/6/25 NA Mon 1/6/25 8 Permits Approved 1 day? NA Mon 1/6/25 NA Mon 1/6/25 9 Mobilazation 1 day? NA Mon 1/6/25 NA Mon 1/6/25 Preperation 10 17 Prep area fro trailers 1 day? and parking 11 Procurement 1 day? 12 Identify materials and 1 day? 금금금 NA Mon 1/6/25 NA Mon 1/6/25 NA Mon 1/6/25 NA Mon 1/6/25 NA Mon 1/6/25 NA Mon 1/6/25 equipment 13 Identify and prequalify 1 day? vendors NA Mon 1/6/25 NA Mon 1/6/25 14 Concrete, Steel, Rebar 1 day? NA Mon 1/6/25 NA Mon 1/6/25 Material purchase 15 Heavy Equipment 1 day? NA Rental 16 Create and issue 1 day? NA RFPs/RFQs 17 Track and manage 1 day? deliveries 18 Inspect deliveries 1 day? on-site 19 Install temporary 1 day? power and internet 20 Sitework 1 day? 21 Land Surveying 1 day? 3 3 3 3 3 3 3 Mon 1/6/25 NA Mon 1/6/25 Mon 1/6/25 NA Mon 1/6/25 NA Mon 1/6/25 NA Mon 1/6/25 NA Mon 1/6/25 NA Mon 1/6/25 NA Mon 1/6/25 NA Mon 1/6/25 Mon 1/6/25 NA Mon 1/6/25 Mon 1/6/25 NA Mon 1/6/25 Ready 45°F Sunny New Tasks: Auto Scheduled Q Search T Task Actual Actual Mode Task Name 22 Duration Start Start Finish - Finish Predecessors Clearing and Grubbing 1 day? 23 Site Grading and 1 day? 금금 NA Mon 1/6/25 NA Mon 1/6/25 NA Mon 1/6/25 NA Mon 1/6/25 Leveling 24 Set up roads and access 1 day? NA Mon 1/6/25 NA Mon 1/6/25 points for deliveries 25 Soil Testing 1 day? NA Mon 1/6/25 NA Mon 1/6/25 26 Excavation 1 day? NA Mon 1/6/25 NA Mon 1/6/25 27 Trenching 1 day? NA Mon 1/6/25 NA Mon 1/6/25 28 Foundation Excavation 1 day? NA Mon 1/6/25 NA Mon 1/6/25 29 Utility Trenching 1 day? NA Mon 1/6/25 NA Mon 1/6/25 30 Backfilling 1 day? NA Mon 1/6/25 NA Mon 1/6/25 31 Utility Installation 1 day? NA Mon 1/6/25 NA Mon 1/6/25 32 Water/Sewer Lines 1 day? NA Mon 1/6/25 NA Mon 1/6/25 33 Electrical Lines 1 day? NA Mon 1/6/25 NA Mon 1/6/25 GANTT CHART 84 Gas Lines 1 day? NA Mon 1/6/25 NA Mon 1/6/25 35 Storm Drain Installation 1 day? NA Mon 1/6/25 NA Mon 1/6/25 36 Grading for Drainage 1 day? NA Mon 1/6/25 NA Mon 1/6/25 37 Foundation Work 1 day? NA Mon 1/6/25 NA Mon 1/6/25 38 Excavate for footings 1 day? NA Mon 1/6/25 NA Mon 1/6/25 and foundation 39 940 Slab preparation 1 day? NA Mon 1/6/25 NA Mon 1/6/25 40 Install formwork and 1 day? NA Mon 1/6/25 NA Mon 1/6/25 reinforcement for footings 41 Install Rebar 1 day? NA Mon 1/6/25 NA Mon 1/6/25 42 Groundwork 1 day? NA Mon 1/6/25 NA Mon 1/6/25 43 Pour Foundation 1 day? NA Mon 1/6/25 NA Mon 1/6/25 44 Curing of Foundation 1 day? NA Mon 1/6/25 NA Mon 1/6/25 45 Concrete pouring for 1 day? NA Mon 1/6/25 NA Mon 1/6/25 footings and walls 46 47 4449 Formwork construction 1 day? NA Mon 1/6/25 NA Mon 1/6/25 Building Structure 1 day? NA Mon 1/6/25 NA Mon 1/6/25 48 Reinforce Steel 1 day? NA Mon 1/6/25 NA Mon 1/6/25 Install Steel Structure 1 day? NA Mon 1/6/25 NA Mon 1/6/25 Ready New Tasks: Auto Scheduled Successors R

Traffic and Highway Engineering
5th Edition
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Garber, Nicholas J.
Chapter21: Pavement Management
Section: Chapter Questions
Problem 7P
icon
Related questions
Question

link activities with predecessors and successors

fill the durations column, actual start, start, actual finish , and finish

 

start date is january 6,2025 as soon as possible

 

help me with this

GANTT CHART
1
2
3
Mon 1/6/25
Add tasks with dat
Task
Mode
Actual
Actual
Task Name
Duration
Start
Start
Finish
▼Finish
Predecessors
Successors
Preconstruction
1 day?
NA
Mon 1/6/25 NA
Define Project scope
5 days
NA
Mon 1/6/25 NA
Mon 1/6/25
Fri 1/10/25
and Objectives
Assemble Project Team 7 days
NA
Mon 1/6/25 NA
Tue 1/14/25
ㄢ
Conduct Site Surveys
10 days
NA
Mon 1/6/25 NA
Fri 1/17/25
and Studies
5
Perform Environmental 1 day?
NA
Mon 1/6/25 NA
Mon 1/6/25
Assessments
6
Submit Plans for
1 day?
NA
Mon 1/6/25 NA
Mon 1/6/25
Permits
7
Obtain Permits
1 day?
NA
Mon 1/6/25 NA
Mon 1/6/25
8
Permits Approved
1 day?
NA
Mon 1/6/25 NA
Mon 1/6/25
9
Mobilazation
1 day?
NA
Mon 1/6/25 NA
Mon 1/6/25
Preperation
10
17
Prep area fro trailers
1 day?
and parking
11
Procurement
1 day?
12
Identify materials and 1 day?
금금금
NA
Mon 1/6/25 NA
Mon 1/6/25
NA
Mon 1/6/25 NA
Mon 1/6/25
NA
Mon 1/6/25 NA
Mon 1/6/25
equipment
13
Identify and prequalify 1 day?
vendors
NA
Mon 1/6/25 NA
Mon 1/6/25
14
Concrete, Steel, Rebar 1 day?
NA
Mon 1/6/25 NA
Mon 1/6/25
Material purchase
15
Heavy Equipment
1 day?
NA
Rental
16
Create and issue
1 day?
NA
RFPs/RFQs
17
Track and manage
1 day?
deliveries
18
Inspect deliveries
1 day?
on-site
19
Install temporary
1 day?
power and internet
20
Sitework
1 day?
21
Land Surveying
1 day?
3 3 3 3 3 3 3
Mon 1/6/25 NA
Mon 1/6/25
Mon 1/6/25 NA
Mon 1/6/25
NA
Mon 1/6/25 NA
Mon 1/6/25
NA
Mon 1/6/25 NA
Mon 1/6/25
NA
Mon 1/6/25 NA
Mon 1/6/25
Mon 1/6/25 NA
Mon 1/6/25
Mon 1/6/25 NA
Mon 1/6/25
Ready
45°F
Sunny
New Tasks: Auto Scheduled
Q Search
Transcribed Image Text:GANTT CHART 1 2 3 Mon 1/6/25 Add tasks with dat Task Mode Actual Actual Task Name Duration Start Start Finish ▼Finish Predecessors Successors Preconstruction 1 day? NA Mon 1/6/25 NA Define Project scope 5 days NA Mon 1/6/25 NA Mon 1/6/25 Fri 1/10/25 and Objectives Assemble Project Team 7 days NA Mon 1/6/25 NA Tue 1/14/25 ㄢ Conduct Site Surveys 10 days NA Mon 1/6/25 NA Fri 1/17/25 and Studies 5 Perform Environmental 1 day? NA Mon 1/6/25 NA Mon 1/6/25 Assessments 6 Submit Plans for 1 day? NA Mon 1/6/25 NA Mon 1/6/25 Permits 7 Obtain Permits 1 day? NA Mon 1/6/25 NA Mon 1/6/25 8 Permits Approved 1 day? NA Mon 1/6/25 NA Mon 1/6/25 9 Mobilazation 1 day? NA Mon 1/6/25 NA Mon 1/6/25 Preperation 10 17 Prep area fro trailers 1 day? and parking 11 Procurement 1 day? 12 Identify materials and 1 day? 금금금 NA Mon 1/6/25 NA Mon 1/6/25 NA Mon 1/6/25 NA Mon 1/6/25 NA Mon 1/6/25 NA Mon 1/6/25 equipment 13 Identify and prequalify 1 day? vendors NA Mon 1/6/25 NA Mon 1/6/25 14 Concrete, Steel, Rebar 1 day? NA Mon 1/6/25 NA Mon 1/6/25 Material purchase 15 Heavy Equipment 1 day? NA Rental 16 Create and issue 1 day? NA RFPs/RFQs 17 Track and manage 1 day? deliveries 18 Inspect deliveries 1 day? on-site 19 Install temporary 1 day? power and internet 20 Sitework 1 day? 21 Land Surveying 1 day? 3 3 3 3 3 3 3 Mon 1/6/25 NA Mon 1/6/25 Mon 1/6/25 NA Mon 1/6/25 NA Mon 1/6/25 NA Mon 1/6/25 NA Mon 1/6/25 NA Mon 1/6/25 NA Mon 1/6/25 NA Mon 1/6/25 Mon 1/6/25 NA Mon 1/6/25 Mon 1/6/25 NA Mon 1/6/25 Ready 45°F Sunny New Tasks: Auto Scheduled Q Search
T
Task
Actual
Actual
Mode
Task Name
22
Duration
Start
Start
Finish
- Finish
Predecessors
Clearing and Grubbing 1 day?
23
Site Grading and
1 day?
금금
NA
Mon 1/6/25 NA
Mon 1/6/25
NA
Mon 1/6/25 NA
Mon 1/6/25
Leveling
24
Set up roads and access 1 day?
NA
Mon 1/6/25 NA
Mon 1/6/25
points for deliveries
25
Soil Testing
1 day?
NA
Mon 1/6/25 NA
Mon 1/6/25
26
Excavation
1 day?
NA
Mon 1/6/25 NA
Mon 1/6/25
27
Trenching
1 day?
NA
Mon 1/6/25 NA
Mon 1/6/25
28
Foundation Excavation
1 day?
NA
Mon 1/6/25 NA
Mon 1/6/25
29
Utility Trenching
1 day?
NA
Mon 1/6/25 NA
Mon 1/6/25
30
Backfilling
1 day?
NA
Mon 1/6/25 NA
Mon 1/6/25
31
Utility Installation
1 day?
NA
Mon 1/6/25 NA
Mon 1/6/25
32
Water/Sewer Lines
1 day?
NA
Mon 1/6/25 NA
Mon 1/6/25
33
Electrical Lines
1 day?
NA
Mon 1/6/25 NA
Mon 1/6/25
GANTT CHART
84
Gas Lines
1 day?
NA
Mon 1/6/25 NA
Mon 1/6/25
35
Storm Drain Installation 1 day?
NA
Mon 1/6/25 NA
Mon 1/6/25
36
Grading for Drainage
1 day?
NA
Mon 1/6/25 NA
Mon 1/6/25
37
Foundation Work
1 day?
NA
Mon 1/6/25 NA
Mon 1/6/25
38
Excavate for footings
1 day?
NA
Mon 1/6/25 NA
Mon 1/6/25
and foundation
39
940
Slab preparation
1 day?
NA
Mon 1/6/25 NA
Mon 1/6/25
40
Install formwork and
1 day?
NA
Mon 1/6/25 NA
Mon 1/6/25
reinforcement for
footings
41
Install Rebar
1 day?
NA
Mon 1/6/25 NA
Mon 1/6/25
42
Groundwork
1 day?
NA
Mon 1/6/25 NA
Mon 1/6/25
43
Pour Foundation
1 day?
NA
Mon 1/6/25 NA
Mon 1/6/25
44
Curing of Foundation
1 day?
NA
Mon 1/6/25 NA
Mon 1/6/25
45
Concrete pouring for
1 day?
NA
Mon 1/6/25 NA
Mon 1/6/25
footings and walls
46
47
4449
Formwork construction 1 day?
NA
Mon 1/6/25 NA
Mon 1/6/25
Building Structure
1 day?
NA
Mon 1/6/25 NA
Mon 1/6/25
48
Reinforce Steel
1 day?
NA
Mon 1/6/25 NA
Mon 1/6/25
Install Steel Structure
1 day?
NA
Mon 1/6/25 NA
Mon 1/6/25
Ready
New Tasks: Auto Scheduled
Successors
R
Transcribed Image Text:T Task Actual Actual Mode Task Name 22 Duration Start Start Finish - Finish Predecessors Clearing and Grubbing 1 day? 23 Site Grading and 1 day? 금금 NA Mon 1/6/25 NA Mon 1/6/25 NA Mon 1/6/25 NA Mon 1/6/25 Leveling 24 Set up roads and access 1 day? NA Mon 1/6/25 NA Mon 1/6/25 points for deliveries 25 Soil Testing 1 day? NA Mon 1/6/25 NA Mon 1/6/25 26 Excavation 1 day? NA Mon 1/6/25 NA Mon 1/6/25 27 Trenching 1 day? NA Mon 1/6/25 NA Mon 1/6/25 28 Foundation Excavation 1 day? NA Mon 1/6/25 NA Mon 1/6/25 29 Utility Trenching 1 day? NA Mon 1/6/25 NA Mon 1/6/25 30 Backfilling 1 day? NA Mon 1/6/25 NA Mon 1/6/25 31 Utility Installation 1 day? NA Mon 1/6/25 NA Mon 1/6/25 32 Water/Sewer Lines 1 day? NA Mon 1/6/25 NA Mon 1/6/25 33 Electrical Lines 1 day? NA Mon 1/6/25 NA Mon 1/6/25 GANTT CHART 84 Gas Lines 1 day? NA Mon 1/6/25 NA Mon 1/6/25 35 Storm Drain Installation 1 day? NA Mon 1/6/25 NA Mon 1/6/25 36 Grading for Drainage 1 day? NA Mon 1/6/25 NA Mon 1/6/25 37 Foundation Work 1 day? NA Mon 1/6/25 NA Mon 1/6/25 38 Excavate for footings 1 day? NA Mon 1/6/25 NA Mon 1/6/25 and foundation 39 940 Slab preparation 1 day? NA Mon 1/6/25 NA Mon 1/6/25 40 Install formwork and 1 day? NA Mon 1/6/25 NA Mon 1/6/25 reinforcement for footings 41 Install Rebar 1 day? NA Mon 1/6/25 NA Mon 1/6/25 42 Groundwork 1 day? NA Mon 1/6/25 NA Mon 1/6/25 43 Pour Foundation 1 day? NA Mon 1/6/25 NA Mon 1/6/25 44 Curing of Foundation 1 day? NA Mon 1/6/25 NA Mon 1/6/25 45 Concrete pouring for 1 day? NA Mon 1/6/25 NA Mon 1/6/25 footings and walls 46 47 4449 Formwork construction 1 day? NA Mon 1/6/25 NA Mon 1/6/25 Building Structure 1 day? NA Mon 1/6/25 NA Mon 1/6/25 48 Reinforce Steel 1 day? NA Mon 1/6/25 NA Mon 1/6/25 Install Steel Structure 1 day? NA Mon 1/6/25 NA Mon 1/6/25 Ready New Tasks: Auto Scheduled Successors R
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Recommended textbooks for you
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning
Residential Construction Academy: House Wiring (M…
Residential Construction Academy: House Wiring (M…
Civil Engineering
ISBN:
9781285852225
Author:
Gregory W Fletcher
Publisher:
Cengage Learning
Architectural Drafting and Design (MindTap Course…
Architectural Drafting and Design (MindTap Course…
Civil Engineering
ISBN:
9781285165738
Author:
Alan Jefferis, David A. Madsen, David P. Madsen
Publisher:
Cengage Learning
Engineering Fundamentals: An Introduction to Engi…
Engineering Fundamentals: An Introduction to Engi…
Civil Engineering
ISBN:
9781305084766
Author:
Saeed Moaveni
Publisher:
Cengage Learning
Construction Materials, Methods and Techniques (M…
Construction Materials, Methods and Techniques (M…
Civil Engineering
ISBN:
9781305086272
Author:
William P. Spence, Eva Kultermann
Publisher:
Cengage Learning
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,