Table 9.3 Fill Factors for Hydraulic Hoe Buckets Moist loam/sandy clay Sand and gravel Rock-poorly blasted Rock-well blasted Hard, tough clay *Percent of heaped bucket capacity. Reprinted courtesy of Caterpillar, Inc. Material Fill Factor* (%) 100-110 95-110 40-50 60-75 80-90 Table 9.4 Excavation Cycle Times for Hydraulic Crawler Hoes under Average Conditions* Bucket Size (cy) <1 Load Bucket (sec) 5 Swing Loaded (sec) Dump Bucket (sec) Swing Empty (sec) Total Cycle (sec) 4 2 3 14 1−1½ 6 4 2 3 15 2-2½ 6 4 3 4 17 3 7 5 4 4 20 312 7 6 4 5 сл 22 4 5 7 7 6 7 4 5 22 4 *Depth of cut 40 to 60% of maximum digging depth; swing angle 30 to 60 degrees; loading haul units on the same level as the excavator 100 6 24

Principles of Foundation Engineering (MindTap Course List)
9th Edition
ISBN:9781337705028
Author:Braja M. Das, Nagaratnam Sivakugan
Publisher:Braja M. Das, Nagaratnam Sivakugan
Chapter5: Soil Improvement And Ground Modification
Section: Chapter Questions
Problem 5.13P
Question

What it the best probable production in lcy/hr for a 3 cy hoe excavating poorly blasted rock?

Assume a 50 minute efficiency.

Use data from Tables 9.3 and 9.4 in the book and assume that the average depth of excavation and the angle of swing fall within the range of average conditions.

Table 9.3 Fill Factors for Hydraulic Hoe Buckets
Moist loam/sandy clay
Sand and gravel
Rock-poorly blasted
Rock-well blasted
Hard, tough clay
*Percent of heaped bucket capacity.
Reprinted courtesy of Caterpillar, Inc.
Material
Fill Factor* (%)
100-110
95-110
40-50
60-75
80-90
Transcribed Image Text:Table 9.3 Fill Factors for Hydraulic Hoe Buckets Moist loam/sandy clay Sand and gravel Rock-poorly blasted Rock-well blasted Hard, tough clay *Percent of heaped bucket capacity. Reprinted courtesy of Caterpillar, Inc. Material Fill Factor* (%) 100-110 95-110 40-50 60-75 80-90
Table 9.4 Excavation Cycle Times for Hydraulic Crawler Hoes under Average Conditions*
Bucket Size (cy)
<1
Load Bucket (sec)
5
Swing Loaded (sec)
Dump Bucket (sec)
Swing Empty (sec)
Total Cycle (sec)
4
2
3
14
1−1½
6
4
2
3
15
2-2½
6
4
3
4
17
3
7
5
4
4
20
312
7
6
4
5
сл
22
4
5
7
7
6
7
4
5
22
4
*Depth of cut 40 to 60% of maximum digging depth; swing angle 30 to 60 degrees; loading haul units on the same level as the excavator
100
6
24
Transcribed Image Text:Table 9.4 Excavation Cycle Times for Hydraulic Crawler Hoes under Average Conditions* Bucket Size (cy) <1 Load Bucket (sec) 5 Swing Loaded (sec) Dump Bucket (sec) Swing Empty (sec) Total Cycle (sec) 4 2 3 14 1−1½ 6 4 2 3 15 2-2½ 6 4 3 4 17 3 7 5 4 4 20 312 7 6 4 5 сл 22 4 5 7 7 6 7 4 5 22 4 *Depth of cut 40 to 60% of maximum digging depth; swing angle 30 to 60 degrees; loading haul units on the same level as the excavator 100 6 24
Expert Solution
steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Similar questions
Recommended textbooks for you
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Construction Materials, Methods and Techniques (M…
Construction Materials, Methods and Techniques (M…
Civil Engineering
ISBN:
9781305086272
Author:
William P. Spence, Eva Kultermann
Publisher:
Cengage Learning
Fundamentals of Geotechnical Engineering (MindTap…
Fundamentals of Geotechnical Engineering (MindTap…
Civil Engineering
ISBN:
9781305635180
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781305081550
Author:
Braja M. Das
Publisher:
Cengage Learning
Principles of Geotechnical Engineering (MindTap C…
Principles of Geotechnical Engineering (MindTap C…
Civil Engineering
ISBN:
9781305970939
Author:
Braja M. Das, Khaled Sobhan
Publisher:
Cengage Learning
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,