Four Squares Productions, a firm hired to coordinate the release of the movie Pirates of the Caribbean: On Stranger Tides (starring Johnny Depp), identified 16 activities to be completed before the release of the film. The appropriate data are shown in the following table: Activity A B с D E F G H Time (weeks) b m 2.0 4.0 3.5 6.0 12.0 14.0 5.0 7.0 4.0 5.0 7.0 8.0 4.0 5.5 7.7 10.0 a 1.0 2.0 10.0 4.0 2.0 5.0 1.0 3.0 This exercise contains only parts a and c. a) Four Squares should start preparing for the release of the movie The activities that represent the project's critical path are Immediate Predecessor(s) A B C c) If it is determined that activities I and J are not necessary, this finding will result in Activity I J K L M N O P a 10.5 2.0 2.0 3.0 5.0 1.0 4.0 5.0 Time (weeks) m b 13.0 14.0 4.0 6.0 4.0 6.0 7.0 7.5 3.0 5.0 6.0 1.1 6.0 6.0 9.0 9.0 to the length of the project. Immediate Predecessor(s) с C D E weeks in advance of the film's release as this is the length of the project. (Round your response to two decimal places.) F, G, H J, K, L I, M N

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Four Squares​ Productions, a firm hired to coordinate the release of the movie Pirates of the​ Caribbean: On Stranger

Tides​ (starring Johnny​ Depp), identified 16 activities to be completed before the release of the film. The appropriate data are shown in the following​ table:

                                                                                                                                                                   

 

Time ​(weeks​)

 

 

 

 

 

Immediate

 

Time ​(weeks​)

 

 

 

 

 

Immediate

Activity

a

 

m

 

b

 

Predecessor(s)

Activity

a

 

m

 

b

 

Predecessor(s)

A

1.0

 

2.0

 

4.0

 

I

10.5

 

13.0

 

14.0

 

C

B

2.0

 

3.5

 

6.0

 

J

2.0

 

4.0

 

6.0

 

C

C

10.0

 

12.0

 

14.0

 

K

2.0

 

4.0

 

6.0

 

D

D

4.0

 

5.0

 

7.0

 

L

3.0

 

5.0

 

7.0

 

E

E

2.0

 

4.0

 

5.0

 

M

5.0

 

6.0

 

7.5

 

F, G, H

F

5.0

 

7.0

 

8.0

 

A

N

1.0

 

1.1

 

3.0

 

J, K, L

G

1.0

 

4.0

 

5.5

 

B

O

4.0

 

6.0

 

9.0

 

I, M

H

3.0

 

7.7

 

10.0

 

C

P

5.0

 

6.0

 

9.0

 

N

This exercise contains only parts a and c.

Part 2

​a) Four Squares should start preparing for the release of the movie

 

enter your response here

weeks in advance of the​ film's release as this is the length of the project. ​(Round your response to two decimal​ places.)

Part 3

The activities that represent the​ project's critical path are

 

C - J - N - P

C - H - M - O

C - I - O

A - F - M - O

E - L - N - P

B - G - M - O

D - K - N - P

.

Part 4

​c) If it is determined that activities

 

I and

 

J are not​ necessary, this finding will result in

 

 

to the length of the project.

 

 

 

 

 

 

Next

 

 

 

 

 

Next

 

 

Next

 

Four Squares Productions, a firm hired to coordinate the release of the movie Pirates of the Caribbean: On Stranger
(starring Johnny Depp), identified 16 activities to be completed before the release of the film. The appropriate data are shown in the following table:
Tides
Activity
A
B
C
D
E
F
G
Time (weeks)
a
1.0
2.0
10.0
4.0
2.0
5.0
1.0
3.0
The activities that represent the project's critical path are
m
2.0
3.5
12.0
5.0
4.0
7.0
4.0
7.7
This exercise contains only parts a and c.
a) Four Squares should start preparing for the release of the movie
b
4.0
6.0
14.0
7.0
5.0
8.0
5.5
10.0
Immediate
Predecessor(s)
A
B
C
c) If it is determined that activities I and J are not necessary, this finding will result in
Activity
1
K
L
M
O
a
10.5
2.0
2.0
3.0
5.0
1.0
4.0
5.0
Time (weeks)
m
13.0
4.0
4.0
5.0
6.0
1.1
6.0
6.0
b
14.0
6.0
6.0
to the length of the project.
7.0
7.5
3.0
9.0
9.0
Immediate
Predecessor(s)
C
D
weeks in advance of the film's release as this is the length of the project. (Round your response to two decimal places.)
E
F, G, H
J, K, L
I, M
Transcribed Image Text:Four Squares Productions, a firm hired to coordinate the release of the movie Pirates of the Caribbean: On Stranger (starring Johnny Depp), identified 16 activities to be completed before the release of the film. The appropriate data are shown in the following table: Tides Activity A B C D E F G Time (weeks) a 1.0 2.0 10.0 4.0 2.0 5.0 1.0 3.0 The activities that represent the project's critical path are m 2.0 3.5 12.0 5.0 4.0 7.0 4.0 7.7 This exercise contains only parts a and c. a) Four Squares should start preparing for the release of the movie b 4.0 6.0 14.0 7.0 5.0 8.0 5.5 10.0 Immediate Predecessor(s) A B C c) If it is determined that activities I and J are not necessary, this finding will result in Activity 1 K L M O a 10.5 2.0 2.0 3.0 5.0 1.0 4.0 5.0 Time (weeks) m 13.0 4.0 4.0 5.0 6.0 1.1 6.0 6.0 b 14.0 6.0 6.0 to the length of the project. 7.0 7.5 3.0 9.0 9.0 Immediate Predecessor(s) C D weeks in advance of the film's release as this is the length of the project. (Round your response to two decimal places.) E F, G, H J, K, L I, M
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.