Following are simplified job cost sheets for three custom jobs at the end of June for Custom Patios. Job Number 102 $ 33,000 17,000 5,610 Materials Labor Overhead Job Number 103 Materials Labor Overhead $ 66,000 26,400 8,712 Job Number 104 Materials Labor $ 45,000 40,000 13,200 Overhead All jobs were started in June. Overhead is applied with a predetermined rate based on direct labor cost. Jobs 102 and 103 were finished in June, and Job 104 will be finished in July. 1. What was the total cost of direct materials requisitioned in June? 2. How much total direct labor cost was incurred in June? 3. How much total cost is transferred to Finished Goods Inventory in June?

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
icon
Concept explainers
Topic Video
Question
Following are simplified job cost sheets for three custom jobs at the end of June
for Custom Patios.
Job Number 102
Materials
Labor
Overhead
$ 33,000
17,000
5,610
Job Number 103
Materials
Labor
Overhead
$ 66,000
26,400
8,712
Job Number 104
Materials
Labor
Overhead
$ 45,000
40,000
13,200
All jobs were started in June. Overhead is applied with a predetermined rate
based on direct labor cost. Jobs 102 and 103 were finished in June, and Job 104
will be finished in July.
1. What was the total cost of direct materials requisitioned in June?
2. How much total direct labor cost was incurred in June?
3. How much total cost is transferred to Finished Goods Inventory in June?
Transcribed Image Text:Following are simplified job cost sheets for three custom jobs at the end of June for Custom Patios. Job Number 102 Materials Labor Overhead $ 33,000 17,000 5,610 Job Number 103 Materials Labor Overhead $ 66,000 26,400 8,712 Job Number 104 Materials Labor Overhead $ 45,000 40,000 13,200 All jobs were started in June. Overhead is applied with a predetermined rate based on direct labor cost. Jobs 102 and 103 were finished in June, and Job 104 will be finished in July. 1. What was the total cost of direct materials requisitioned in June? 2. How much total direct labor cost was incurred in June? 3. How much total cost is transferred to Finished Goods Inventory in June?
Complete this question by entering your answers in the tabs below.
Req 1 and 2
Reg 3
1. What was the total cost of direct materials requisitioned in June?
2. How. much total direct labor cost was incurred in June?
Direct Materials
Job
June
102
103
104
Total
Direct Labor
Job
June
102
103
104
Total
Req 1 and 2
Req 3 >
Complete this question by entering your answers in the tabs below.
Reg 1 and 2
Req 3
How much total cost is transferred to Finished Goods Inventory in June?
Direct
Materials
Direct
Labor
Applied
Overhead
Cost Transferred to
Finished Goods
Job
Total Cost
102
2$
17,000
103
26,400
104
40,000
Total
$
83,400
< Req 1 and 2
Req 3>
Transcribed Image Text:Complete this question by entering your answers in the tabs below. Req 1 and 2 Reg 3 1. What was the total cost of direct materials requisitioned in June? 2. How. much total direct labor cost was incurred in June? Direct Materials Job June 102 103 104 Total Direct Labor Job June 102 103 104 Total Req 1 and 2 Req 3 > Complete this question by entering your answers in the tabs below. Reg 1 and 2 Req 3 How much total cost is transferred to Finished Goods Inventory in June? Direct Materials Direct Labor Applied Overhead Cost Transferred to Finished Goods Job Total Cost 102 2$ 17,000 103 26,400 104 40,000 Total $ 83,400 < Req 1 and 2 Req 3>
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Costing Systems
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education