ABC Company uses job costing. Its annual estimated manufacturing overhead and machine hours (the allocation base) were $100,000 and 2,000 hours, respectively. Job 02-03 was completed in June and incurred direct materials of $4,000, direct labor $3,000, and 100 machine hours. Which of the following is the total cost of job 02-03? a) $7,000 b) $107,000 c) $12,000 d) $112,000
Process Costing
Process costing is a sort of operation costing which is employed to determine the value of a product at each process or stage of producing process, applicable where goods produced from a series of continuous operations or procedure.
Job Costing
Job costing is adhesive costs of each and every job involved in the production processes. It is an accounting measure. It is a method which determines the cost of specific jobs, which are performed according to the consumer’s specifications. Job costing is possible only in businesses where the production is done as per the customer’s requirement. For example, some customers order to manufacture furniture as per their needs.
ABC Costing
Cost Accounting is a form of managerial accounting that helps the company in assessing the total variable cost so as to compute the cost of production. Cost accounting is generally used by the management so as to ensure better decision-making. In comparison to financial accounting, cost accounting has to follow a set standard ad can be used flexibly by the management as per their needs. The types of Cost Accounting include – Lean Accounting, Standard Costing, Marginal Costing and Activity Based Costing.
ABC Company uses job costing. Its annual estimated manufacturing
a) $7,000
b) $107,000
c) $12,000
d) $112,000