At the end of April, Cavy Company had completed Jobs 766 and 765. The individual job cost sheets reveal the following information: Job Direct Materials Direct Labor Machine Hours Job No. 765 $5,670 $3,500 27 Job No. 766 8,900 4,775 44 Job 765 produced 152 units, and Job 766 consisted of 250 units. Assuming that the predetermined overhead rate is applied by using machine hours at a rate of $200 per hour. a. Determine the balance on the job cost sheets for each job. Job 765 $ Job 766 $ b. Determine the cost per unit at the end of April. Round your answers to the nearest cent. Job 765 $ Job 766 $
Process Costing
Process costing is a sort of operation costing which is employed to determine the value of a product at each process or stage of producing process, applicable where goods produced from a series of continuous operations or procedure.
Job Costing
Job costing is adhesive costs of each and every job involved in the production processes. It is an accounting measure. It is a method which determines the cost of specific jobs, which are performed according to the consumer’s specifications. Job costing is possible only in businesses where the production is done as per the customer’s requirement. For example, some customers order to manufacture furniture as per their needs.
ABC Costing
Cost Accounting is a form of managerial accounting that helps the company in assessing the total variable cost so as to compute the cost of production. Cost accounting is generally used by the management so as to ensure better decision-making. In comparison to financial accounting, cost accounting has to follow a set standard ad can be used flexibly by the management as per their needs. The types of Cost Accounting include – Lean Accounting, Standard Costing, Marginal Costing and Activity Based Costing.
At the end of April, Cavy Company had completed Jobs 766 and 765. The individual
Job | Direct Materials | Direct Labor | Machine Hours |
Job No. 765 | $5,670 | $3,500 | 27 |
Job No. 766 | 8,900 | 4,775 | 44 |
Job 765 produced 152 units, and Job 766 consisted of 250 units.
Assuming that the predetermined
a. Determine the balance on the job cost sheets for each job.
Job 765 | $ |
Job 766 | $ |
b. Determine the cost per unit at the end of April. Round your answers to the nearest cent.
Job 765 | $ |
Job 766 | $ |