estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2020, 2021, and 2022. At At At 12/31/20 12/31/21 12/31/22 Contract costs incurred to date $327,800 $ 1,180,000 $2,090,400 Estimated costs to complete the contract 1,162,200 820,000 -0- Billings to Gumbel 300,000 1,110,000 1,870,000 (a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2020, 2021, and 2022. (Ignore income taxes.) (If answer is 0, please enter 0. Do not leave any field blank. If an amount should be deducted then enter the amount using eithera negative sign prececeding the number e-g. -45 or parenthesis es. (45).)

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question
**Current Attempt in Progress**

On July 1, 2020, Crane Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,910,000. On July 1, Crane estimated it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2020, 2021, and 2022.

|                         | At 12/31/20 | At 12/31/21 | At 12/31/22 |
|-------------------------|-------------|-------------|-------------|
| Contract costs incurred to date | $327,800     | $1,180,000    | $2,090,400     |
| Estimated costs to complete the contract | $1,162,200   | $820,000      | -0-         |
| Billings to Gumbel            | 300,000     | 1,110,000    | 1,870,000     |

(a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2020, 2021, and 2022. (Ignore income taxes.) *(If answer is 0, please enter 0. Do not leave any field blank. If an amount should be deducted then enter the amount using either a negative sign preceding the number e.g. -45 or parenthesis e.g. (45).)*
Transcribed Image Text:**Current Attempt in Progress** On July 1, 2020, Crane Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,910,000. On July 1, Crane estimated it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2020, 2021, and 2022. | | At 12/31/20 | At 12/31/21 | At 12/31/22 | |-------------------------|-------------|-------------|-------------| | Contract costs incurred to date | $327,800 | $1,180,000 | $2,090,400 | | Estimated costs to complete the contract | $1,162,200 | $820,000 | -0- | | Billings to Gumbel | 300,000 | 1,110,000 | 1,870,000 | (a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2020, 2021, and 2022. (Ignore income taxes.) *(If answer is 0, please enter 0. Do not leave any field blank. If an amount should be deducted then enter the amount using either a negative sign preceding the number e.g. -45 or parenthesis e.g. (45).)*
## Project Cost Overview for 2021 and 2022

### 2021 Financial Data:

1. **Costs to date (12/31/21):** 
   - Amount: $1,180,000

2. **Estimated Costs to Complete:**
   - Amount: $820,000
   
3. **Estimated Total Costs:**
   - Amount: $2,000,000

4. **Contract Price:** 
   - [Field for entry]

5. **Total Profit/Loss:**
   - [Field for entry]

6. **Gross Profit Recognized in 2020:** 
   - [Field for entry]

7. **Profit/(Loss) Recognized in 2021:** 
   - [Field for entry]

---

### 2022 Financial Data:

1. **Costs to date (12/31/22):**
   - Amount: $2,090,400

2. **Estimated Costs to Complete:**
   - [Field for entry]

3. **Contract Price:** 
   - [Field for entry]

4. **Total Profit/Loss:**
   - [Field for entry]

5. **Profit/(Loss) Recognized in 2021:** 
   - [Field for entry]

6. **Profit/(Loss) Recognized in 2020:** 
   - [Field for entry]

7. **Profit/(Loss) Recognized in 2022:** 
   - [Field for entry]

### Explanation:

The table provides a detailed comparison of the project costs for two consecutive years, 2021 and 2022. Each section outlines the actual costs incurred by the end of each year, estimated costs to complete the project, and spaces for inputting contract price and profit/loss figures. The table is formatted to help educators and students track financial data and analyze profitability over time.
Transcribed Image Text:## Project Cost Overview for 2021 and 2022 ### 2021 Financial Data: 1. **Costs to date (12/31/21):** - Amount: $1,180,000 2. **Estimated Costs to Complete:** - Amount: $820,000 3. **Estimated Total Costs:** - Amount: $2,000,000 4. **Contract Price:** - [Field for entry] 5. **Total Profit/Loss:** - [Field for entry] 6. **Gross Profit Recognized in 2020:** - [Field for entry] 7. **Profit/(Loss) Recognized in 2021:** - [Field for entry] --- ### 2022 Financial Data: 1. **Costs to date (12/31/22):** - Amount: $2,090,400 2. **Estimated Costs to Complete:** - [Field for entry] 3. **Contract Price:** - [Field for entry] 4. **Total Profit/Loss:** - [Field for entry] 5. **Profit/(Loss) Recognized in 2021:** - [Field for entry] 6. **Profit/(Loss) Recognized in 2020:** - [Field for entry] 7. **Profit/(Loss) Recognized in 2022:** - [Field for entry] ### Explanation: The table provides a detailed comparison of the project costs for two consecutive years, 2021 and 2022. Each section outlines the actual costs incurred by the end of each year, estimated costs to complete the project, and spaces for inputting contract price and profit/loss figures. The table is formatted to help educators and students track financial data and analyze profitability over time.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education