Assume that Sunland Construction Company has a non-cancellable contract to construct a $4,520,000 bridge at an estimated cost of $4,068,000. The contract is to start in July 2023, and the bridge is to be completed in October 2025. The following data pertain to the construction period. Assume that progress billings are non-refundable. Costs to date (12/31) Estimated costs to complete (12/31) Progress billings during the year Cash collected during the year Contract price Estimated total cost Estimated gross profit Estimated loss 2023 "$2,928,960+ $1,647,540 $1,017,000 The revised estimates for the bridge contract are as follows. 3,051,000 968,000 817,000 2024 $2,928,960 1,647,540 2,418,000 1,897,000 4,068,000 $452,000 2025 $4,576,500 1.134,000 2023 Original Estimates 2024 Revised Estimates $4,520,000 $4,520,000 4,576,500 0 1,806,000 $(56,500) Under the percentage-of-completion method, how would Sunland record the long-term contract revenues, expenses, and losses in 2024. Please show all steps

Intermediate Accounting: Reporting And Analysis
3rd Edition
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Chapter17: Advanced Issues In Revenue Recognition
Section: Chapter Questions
Problem 26E
icon
Related questions
Question
Assume that Sunland Construction Company has a non-cancellable contract to construct a $4,520,000 bridge at an estimated cost of
$4,068,000. The contract is to start in July 2023, and the bridge is to be completed in October 2025. The following data pertain to the
construction period. Assume that progress billings are non-refundable.
Costs to date (12/31)
Estimated costs to complete (12/31)
Progress billings during the year
Cash collected during the year
Contract price
Estimated total cost
Estimated gross profit
Estimated loss.
2023
*$2,928,960+ $1,647,540
$1,017,000
3,051,000
968,000
817,000
The revised estimates for the bridge contract are as follows.
2024
$2,928,960
1,647,540
2,418,000
1,897,000
2025
$4,576,500
1,134,000
0
1,806,000
2023 Original Estimates 2024 Revised Estimates
$4,520,000
$4,520,000
4,068,000
4,576,500*
$452,000
$(56,500)
Under the percentage-of-completion
method, how would Sunland record
the long-term contract revenues,
expenses, and losses in 2024.
Please show all steps
Transcribed Image Text:Assume that Sunland Construction Company has a non-cancellable contract to construct a $4,520,000 bridge at an estimated cost of $4,068,000. The contract is to start in July 2023, and the bridge is to be completed in October 2025. The following data pertain to the construction period. Assume that progress billings are non-refundable. Costs to date (12/31) Estimated costs to complete (12/31) Progress billings during the year Cash collected during the year Contract price Estimated total cost Estimated gross profit Estimated loss. 2023 *$2,928,960+ $1,647,540 $1,017,000 3,051,000 968,000 817,000 The revised estimates for the bridge contract are as follows. 2024 $2,928,960 1,647,540 2,418,000 1,897,000 2025 $4,576,500 1,134,000 0 1,806,000 2023 Original Estimates 2024 Revised Estimates $4,520,000 $4,520,000 4,068,000 4,576,500* $452,000 $(56,500) Under the percentage-of-completion method, how would Sunland record the long-term contract revenues, expenses, and losses in 2024. Please show all steps
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Intermediate Accounting: Reporting And Analysis
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning