equirement 1. Show computations of price and efficiency variances for direct materials and direct manufacturing labor. Give a plausible explanation of why each variance occurred. Let's begin by determining the formula used to calculate the actual costs of direct materials, then enter the amounts in the formula and calculate the cost. × = Actual cost Direct materials × = Next we will calculate the actual input at the budgeted price. Actual input × Budgeted price = Cost Direct materials × = Direct manufacturing labor × =
equirement 1. Show computations of price and efficiency variances for direct materials and direct manufacturing labor. Give a plausible explanation of why each variance occurred. Let's begin by determining the formula used to calculate the actual costs of direct materials, then enter the amounts in the formula and calculate the cost. × = Actual cost Direct materials × = Next we will calculate the actual input at the budgeted price. Actual input × Budgeted price = Cost Direct materials × = Direct manufacturing labor × =
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
Related questions
Question
Davidow,
Inc. is a privately held furniture manufacturer. For August
2020,
Davidow
had the following standards for one of its products, a wicker chair:LOADING...
(ClickThe following data were compiled regarding actual
manufacturing labor costs ,
performance:
actual output units (chairs) produced,
2,800;
square yards of input purchased and used,
5,300;
price per square yard,
$6.00;
direct $9,360;
actual hours of input,
900;
labor price per hour,
$10.40.
.
Requirement 1. Show computations of price and efficiency variances for direct materials and direct manufacturing labor. Give a plausible explanation of why each variance occurred.
Let's begin by determining the formula used to calculate the actual costs of direct materials, then enter the amounts in the formula and calculate the cost.
|
|
×
|
|
=
|
Actual cost
|
Direct materials
|
|
×
|
|
=
|
|
Next we will calculate the actual input at the budgeted price.
|
Actual input
|
×
|
Budgeted price
|
=
|
Cost
|
Direct materials
|
|
×
|
|
=
|
|
Direct manufacturing labor
|
|
×
|
|
=
|
|
Determine the formula and calculate the costs for the flexible budget.
|
|
×
|
|
=
|
Flexible budget cost
|
Direct materials
|
|
×
|
|
=
|
|
Direct manufacturing labor
|
|
×
|
|
=
|
|
Now compute the price and efficiency variances for direct materials and direct manufacturing labor. Label each variance as favorable (F) or unfavorable (U).
|
Price
|
Efficiency
|
||
|
variances
|
variances
|
||
Direct materials
|
|
|
|
|
Direct manufacturing labor
|
|
|
|
|
Now give a plausible explanation of why each variance occurred. Begin with the direct material variances.
The materials price variance: There was an unexpected
in materials price per square yard due to
competition.
▼
decrease
increase
▼
decreased
increased
The materials efficiency variance: The production manager may have employed
workers or the budgeted materials standards were set too
.
▼
higher-skilled
lower-skilled
▼
loosely
strictly
The labor price variance:
in labor rates due to a
.
▼
An increase
A reduction
▼
booming economy
recession
The labor efficiency variance:
efficient workers being employed or the use of
quality materials.
▼
Less
More
▼
higher
lower
Requirement 2. Suppose
7,700
square yards of materials were purchased (at
$6.00
per square yard), even though only
5,300
square yards were used. Suppose further that variances are identified at their most timely control point; accordingly, direct materials price variances are isolated and traced at the time of purchase to the purchasing department rather than to the production department. Compute the price and efficiency variances under this approach.Begin with recalculating the costs using the information provided for the alternative approach.
Actual input
|
|||
×
|
|||
|
Actual cost
|
Budgeted price
|
Flexible budget cost
|
Purchasing
|
|
|
|
Production
|
|
|
|
Now compute the direct materials price and efficiency variances. Label each variance as favorable (F) or unfavorable (U).
|
Price
|
Efficiency
|
||
|
variance
|
variance
|
||
Direct materials
|
|
|
|
|
Choose from any list or enter any number in the input fields and then continue to the next question.
|
|
|
Data Table
|
Standards per Chair
|
Direct materials
|
2 square yards of input at $5.80 per square yard
|
---|---|
Direct manufacturing labor
|
0.5 hour of input at $10.60 per hour
|
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Recommended textbooks for you
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education