Elite Sports Equipment has established the following standards for the prime costs of one unit of its premium basketball: Standard Quantity Standard Price/Rate Standard Cost Component Direct material 4.50 pounds Direct labor 1.25 hours Total $3.40 per pound $15.30 $8.50 per hour $10.63 $25.93 During September, Elite purchased 128,000 pounds of direct material at a total cost of $448,000. The total wages for September were $320,000, 85% of which were for direct labor. Elite manufactured 28,000 basketballs during September, using 122,000 pounds of the direct material purchased in September and 34,500 direct-labor hours. Compute the direct material price variance for September.

Managerial Accounting
15th Edition
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:Carl Warren, Ph.d. Cma William B. Tayler
Chapter13: Lean Manufacturing And Activity Analysis
Section: Chapter Questions
Problem 14E
icon
Related questions
Question
100%

need correct answer of this general accounting

Elite Sports Equipment has established the following standards for the
prime costs of one unit of its premium basketball:
Standard Quantity Standard Price/Rate Standard Cost
Component
Direct material 4.50 pounds
Direct labor 1.25 hours
Total
$3.40 per pound
$15.30
$8.50 per hour
$10.63
$25.93
During September, Elite purchased 128,000 pounds of direct material at a
total cost of $448,000. The total wages for September were $320,000,
85% of which were for direct labor. Elite manufactured 28,000
basketballs during September, using 122,000 pounds of the direct material
purchased in September and 34,500 direct-labor hours.
Compute the direct material price variance for September.
Transcribed Image Text:Elite Sports Equipment has established the following standards for the prime costs of one unit of its premium basketball: Standard Quantity Standard Price/Rate Standard Cost Component Direct material 4.50 pounds Direct labor 1.25 hours Total $3.40 per pound $15.30 $8.50 per hour $10.63 $25.93 During September, Elite purchased 128,000 pounds of direct material at a total cost of $448,000. The total wages for September were $320,000, 85% of which were for direct labor. Elite manufactured 28,000 basketballs during September, using 122,000 pounds of the direct material purchased in September and 34,500 direct-labor hours. Compute the direct material price variance for September.
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Managerial Accounting
Managerial Accounting
Accounting
ISBN:
9781337912020
Author:
Carl Warren, Ph.d. Cma William B. Tayler
Publisher:
South-Western College Pub