ecently, Phil Harris, the production control manager at Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown on the next page. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram below. Phil noted that the gear box is assembled by the Subassembly Department and subsequently is sent to the main engine assembly line. The input shaft is one of several component parts manufactured by Brunswick that are needed to produce a gear box subassembly. Thus, levels 0, 1, and 2 are included in the product structure diagram to indicate the three manufacturing stages that are involved in producing an engine: the Engine Assembly Department, the Subassembly Department, and the Machine Shop. The manufacturing lead times required to produce the gear box and input shaft components are also indicated in the product structure diagram. Note that two weeks are required to produce a batch of gear boxes and that all the gear boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of input shafts, and all the shafts that are needed for the production of gear boxes in a given week must be delivered to the Subassembly Department stockroom before Monday morning of that week. In preparing the MRP example Phil planned to use the worksheets shown and to make the following assumptions: 1. Twenty gear boxes are on hand at the beginning of Week 1, and six gear boxes are currently on order to be delivered at the start of Week 2. 2. Forty input shafts are on hand at the start of Week 1, and 24 are scheduled for delivery at the beginning of Week 2. a. Initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot (L4L). (Leave no cells blank - be certain to enter "0" wherever required.) Gear Box Requirements Input Shaft Requirements Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. These costs are as follows: PART COST Gear Box Setup = $80/order Inventory carrying cost = $3/unit/week Input Shaft Setup = $50/order Inventory carrying cost = $2/unit/week Suppose least-total-cost lot sizing is to be used. Using the planned order receipts shown below, complete the remainder of the gear box and input shaft tables. (Leave no cells blank - be certain to enter "0" wherever required.) Gear Box Requirements Input Shaft Requirements c. What are the savings with the new schedule? Assume inventory is valued at the end of each week. Cost of the schedule from part (a) Cost of the schedule using least-total-cost lot sizing. Savings with the new schedule.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
icon
Concept explainers
Topic Video
Question

ecently, Phil Harris, the production control manager at Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning.

 

Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown on the next page. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram below. Phil noted that the gear box is assembled by the Subassembly Department and subsequently is sent to the main engine assembly line. The input shaft is one of several component parts manufactured by Brunswick that are needed to produce a gear box subassembly. Thus, levels 0, 1, and 2 are included in the product structure diagram to indicate the three manufacturing stages that are involved in producing an engine: the Engine Assembly Department, the Subassembly Department, and the Machine Shop.

 

The manufacturing lead times required to produce the gear box and input shaft components are also indicated in the product structure diagram. Note that two weeks are required to produce a batch of gear boxes and that all the gear boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of input shafts, and all the shafts that are needed for the production of gear boxes in a given week must be delivered to the Subassembly Department stockroom before Monday morning of that week.

 

In preparing the MRP example Phil planned to use the worksheets shown and to make the following assumptions:

 

  1. 1. Twenty gear boxes are on hand at the beginning of Week 1, and six gear boxes are currently on order to be delivered at the start of Week 2.

  2.  

  3. 2. Forty input shafts are on hand at the start of Week 1, and 24 are scheduled for delivery at the beginning of Week 2.

  4.  

 

 

 

 

a. Initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot (L4L). (Leave no cells blank - be certain to enter "0" wherever required.)

 

Gear Box Requirements

 

 

 

 

Input Shaft Requirements

 

 

 

 

Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. These costs are as follows:

 

PART COST
Gear Box Setup = $80/order
Inventory carrying cost = $3/unit/week
Input Shaft Setup = $50/order
Inventory carrying cost = $2/unit/week
 

 

Suppose least-total-cost lot sizing is to be used. Using the planned order receipts shown below, complete the remainder of the gear box and input shaft tables. (Leave no cells blank - be certain to enter "0" wherever required.)

 

Gear Box Requirements

 

 

 

 

Input Shaft Requirements  

 

 

 

 

c. What are the savings with the new schedule? Assume inventory is valued at the end of each week.  

 

Cost of the schedule from part (a)

 

 

 

 

Cost of the schedule using least-total-cost lot sizing.

 

 

 

 

Savings with the new schedule.

 

 

 

 

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 5 images

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.