Earned Value Management (EVM) is a method or an approach in measuring the project performance throughout the project at any point of time that integrates the variances of cost and schedule in assisting organizations to decide either to continue or terminate the project. 1. List FIVE benefits of EVM method in assuring the successful implementation of project 2. Within 200 days, the equipment supplier has agreed to supply 100 units of spare equipment at the price of RM500 per unit. However, 50 days later, the supplier can only supply 21 units with an actual total cost of RM11,400. a. Indicate either the supply is ahead or behind the schedule (in days). b. Indicate either the supply is under or exceed the budget (in amount). c. Indicate the cost performance of the supply (in percentage) d Indicate the performance of the supply in term of schedule (in percentage)

Managerial Economics: Applications, Strategies and Tactics (MindTap Course List)
14th Edition
ISBN:9781305506381
Author:James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Chapter17: Long-term Investment Analysis
Section: Chapter Questions
Problem 10E
icon
Related questions
Question

only answer question 3 (number 2) .

QUESTION 3
Earned Value Management (EVM) is a method or an approach in measuring the project performance
throughout the project at any point of time that integrates the variances of cost and schedule in
assisting organizations to decide either to continue or terminate the project.
1. List FIVE benefits of EVM method in assuring the successful implementation of project
2. Within 200 days, the equipment supplier has agreed to supply 100 units of spare equipment at the
price of RM500 per unit. However, 50 days later, the supplier can only supply 21 units with an
actual total cost of RM11,400.
a. Indicate either the supply is ahead or behind the schedule (in days).
b. Indicate either the supply is under or exceed the budget (in amount).
c. Indicate the cost performance of the supply (in percentage)
d. Indicate the performance of the supply in term of schedule (in percentage)
Transcribed Image Text:QUESTION 3 Earned Value Management (EVM) is a method or an approach in measuring the project performance throughout the project at any point of time that integrates the variances of cost and schedule in assisting organizations to decide either to continue or terminate the project. 1. List FIVE benefits of EVM method in assuring the successful implementation of project 2. Within 200 days, the equipment supplier has agreed to supply 100 units of spare equipment at the price of RM500 per unit. However, 50 days later, the supplier can only supply 21 units with an actual total cost of RM11,400. a. Indicate either the supply is ahead or behind the schedule (in days). b. Indicate either the supply is under or exceed the budget (in amount). c. Indicate the cost performance of the supply (in percentage) d. Indicate the performance of the supply in term of schedule (in percentage)
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Depletion Allowance
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Managerial Economics: Applications, Strategies an…
Managerial Economics: Applications, Strategies an…
Economics
ISBN:
9781305506381
Author:
James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:
Cengage Learning
EBK HEALTH ECONOMICS AND POLICY
EBK HEALTH ECONOMICS AND POLICY
Economics
ISBN:
9781337668279
Author:
Henderson
Publisher:
YUZU