Develop a minimum makespan schedule using Johnson's rule. The schedule using Johnson's rule is - - - - - . Choose the correct Gantt chart with the minimum makespan schedule. The correct graph is
Develop a minimum makespan schedule using Johnson's rule. The schedule using Johnson's rule is - - - - - . Choose the correct Gantt chart with the minimum makespan schedule. The correct graph is
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
On Monday morning, Baxter Industries has the following jobs waiting for processing in two departments, milling, and drilling, in that order.
Time Required (hours) | ||||
Job | Mill | Drill | ||
216 | 7 | 11 | ||
327 | 6 | 10 | ||
462 | 8 | 4 | ||
519 | 5 | 8 | ||
258 | 3 | 5 | ||
617 | 12 | 15 |
Develop a minimum makespan
The schedule using Johnson's rule is - - - - - .
Choose the correct Gantt chart with the minimum makespan schedule.
The correct graph is .

Transcribed Image Text:The image consists of two sections, labeled C and D, each showing timelines for "MILL" and "DRILL" operations. These timelines indicate a sequence of jobs completed over specific time intervals.
### Section C:
#### MILL Operation:
- **Time Intervals:** 0, 3, 8, 14, 21, 29, 41
- **Jobs:** 258, 519, 327, 216, 462, 617
The timeline shows when each job is completed during the MILL operation. The intervals indicate the start of processing each job.
#### DRILL Operation:
- **Time Intervals:** 0, 3, 8, 16, 26, 37, 41
- **Jobs:** 258, 519, 327, 216, 462, 617
This timeline mirrors the structure of the MILL operation but with different time markers for job completion.
### Section D:
#### MILL Operation:
- **Time Intervals:** 0, 8, 20, 27, 33, 38, 41
- **Jobs:** 462, 617, 216, 327, 519, 258
The time intervals here highlight a different sequencing of jobs compared to Section C.
#### DRILL Operation:
- **Time Intervals:** 0, 8, 12, 35, 46, 56, 64, 69
- **Jobs:** 462, 617, 216, 327, 519, 258
This operation's timeline extends further, reflecting more job completions over a longer period compared to the MILL operation in this section.
### Overall Observation:
The diagrams provide a visual representation of job scheduling in two different operation processes, highlighting differences in time intervals and job order between MILL and DRILL operations across sections C and D.
![On Monday morning, Baxter Industries has the following jobs waiting for processing in two departments, milling, and drilling, in that order.
| Job | Time Required (hours) |
|-----|-----------------------|
| | Mill | Drill |
| 216 | 7 | 11 |
| 327 | 6 | 10 |
| 462 | 8 | 4 |
| 519 | 5 | 8 |
| 258 | 3 | 5 |
| 617 | 12 | 15 |
Develop a minimum makespan schedule using Johnson's rule.
The schedule using Johnson's rule is [Select -] - [Select -] - [Select -] - [Select -] - [Select -] - [Select -].
Choose the correct Gantt chart with the minimum makespan schedule.
The correct graph is [Select -].
**Gantt Charts**
**A.**
- **MILL**
- Time: 0 | 3 | 8 | 14 | 21 | 33 | 41
- Job: 258 | 519 | 327 | 216 | 617 | 462
- **DRILL**
- Time: 0 | 3 | 8 | 16 | 26 | 37 | 52 | 56
- Job: 258 | 519 | 327 | 216 | 617 | 462
**B.**
- **MILL**
- Time: 0 | 7 | 13 | 21 | 26 | 29 | 41
- Job: 216 | 327 | 462 | 519 | 258 | 617
These Gantt charts illustrate the processing times for each job in the mill and drill departments. The charts detail the sequence and time intervals for each job's completion.](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F397f2041-1212-4097-b8a0-c62cdf27e29e%2F4a8b5d53-bea4-4a45-96dc-c0b52e2e8a7e%2Ffzziqft_processed.png&w=3840&q=75)
Transcribed Image Text:On Monday morning, Baxter Industries has the following jobs waiting for processing in two departments, milling, and drilling, in that order.
| Job | Time Required (hours) |
|-----|-----------------------|
| | Mill | Drill |
| 216 | 7 | 11 |
| 327 | 6 | 10 |
| 462 | 8 | 4 |
| 519 | 5 | 8 |
| 258 | 3 | 5 |
| 617 | 12 | 15 |
Develop a minimum makespan schedule using Johnson's rule.
The schedule using Johnson's rule is [Select -] - [Select -] - [Select -] - [Select -] - [Select -] - [Select -].
Choose the correct Gantt chart with the minimum makespan schedule.
The correct graph is [Select -].
**Gantt Charts**
**A.**
- **MILL**
- Time: 0 | 3 | 8 | 14 | 21 | 33 | 41
- Job: 258 | 519 | 327 | 216 | 617 | 462
- **DRILL**
- Time: 0 | 3 | 8 | 16 | 26 | 37 | 52 | 56
- Job: 258 | 519 | 327 | 216 | 617 | 462
**B.**
- **MILL**
- Time: 0 | 7 | 13 | 21 | 26 | 29 | 41
- Job: 216 | 327 | 462 | 519 | 258 | 617
These Gantt charts illustrate the processing times for each job in the mill and drill departments. The charts detail the sequence and time intervals for each job's completion.
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 3 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.