Curtiss Construction Company, Incorporated, entered into a fixed-price contract with Axelrod Associates on July 1, 2024, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,360,000. The building was completed on December 31, 2026. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the contract were as follows: Percentage of completion Costs incurred to date Estimated costs to complete Billings to Axelrod, to date Required: At 12-31-2024 At 12-31-2025 At 12-31-2026 10% 60% 100% $ 365,000 3,285,000 726,000 $ 2,772,000 1,848,000 2,290,000 $ 4,676,000 0 4,360,000 1. Compute gross profit or loss to be recognized as a result of this contract for each of the three years. Curtiss concludes that the contract does not qualify for revenue recognition over time. 2. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute gross profit or loss to be recognized in each of the three years. 3. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute the amount to be shown in the balance sheet at the end of 2024 and 2025 as either cost in excess of billings or billings in excess of costs. Complete this question by entering your answers in the tabs below. Req 1 and 2 Req 3 1. Compute gross profit or loss to be recognized as a result of this contract for each of the three years. Curtiss concludes that the contract does not qualify for revenue recognition over time. 2. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute gross profit or loss to be recognized in each of the three years. Note: Leave no cells blank - be certain to enter "0" wherever required. Loss amounts should be indicated with a minus sign. Show less▲ Req 2 Gross Profit (Loss) Recognized ("Over Time") Req 1 Gross Profit (Loss) Recognized Year ("Upon Completion") 2024 $ 0 2025 2026 Total project profit (loss) $ 0 $ < Req 1 and 2 0 Req 3 > Assuming Curtiss recognizes revenue over time according to percentage of completion, compute the amount to be shown in the balance sheet at the end of 2024 and 2025 as either cost in excess of billings or billings in excess of costs. Balance Sheet (Partial) Current assets: Current liabilities: 2024 2025 < Req 1 and 2 Req 3 >

Intermediate Accounting: Reporting And Analysis
3rd Edition
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Chapter17: Advanced Issues In Revenue Recognition
Section: Chapter Questions
Problem 9MC
icon
Related questions
Question
Curtiss Construction Company, Incorporated, entered into a fixed-price contract with Axelrod Associates on July 1, 2024, to construct a
four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The
total contract price for construction of the building is $4,360,000. The building was completed on December 31, 2026. Estimated
percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to
Axelrod under the contract were as follows:
Percentage of completion
Costs incurred to date
Estimated costs to complete
Billings to Axelrod, to date
Required:
At 12-31-2024
At 12-31-2025
At 12-31-2026
10%
60%
100%
$ 365,000
3,285,000
726,000
$ 2,772,000
1,848,000
2,290,000
$ 4,676,000
0
4,360,000
1. Compute gross profit or loss to be recognized as a result of this contract for each of the three years. Curtiss concludes that the
contract does not qualify for revenue recognition over time.
2. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute gross profit or loss to be
recognized in each of the three years.
3. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute the amount to be shown in the
balance sheet at the end of 2024 and 2025 as either cost in excess of billings or billings in excess of costs.
Complete this question by entering your answers in the tabs below.
Req 1 and 2
Req 3
1. Compute gross profit or loss to be recognized as a result of this contract for each of the three years. Curtiss concludes that
the contract does not qualify for revenue recognition over time. 2. Assuming Curtiss recognizes revenue over time according
to percentage of completion, compute gross profit or loss to be recognized in each of the three years.
Note: Leave no cells blank - be certain to enter "0" wherever required. Loss amounts should be indicated with a minus sign.
Show less▲
Req 2
Gross Profit (Loss) Recognized
("Over Time")
Req 1
Gross Profit (Loss) Recognized
Year
("Upon Completion")
2024
$
0
2025
2026
Total project profit (loss)
$
0
$
< Req 1 and 2
0
Req 3 >
Transcribed Image Text:Curtiss Construction Company, Incorporated, entered into a fixed-price contract with Axelrod Associates on July 1, 2024, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,360,000. The building was completed on December 31, 2026. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the contract were as follows: Percentage of completion Costs incurred to date Estimated costs to complete Billings to Axelrod, to date Required: At 12-31-2024 At 12-31-2025 At 12-31-2026 10% 60% 100% $ 365,000 3,285,000 726,000 $ 2,772,000 1,848,000 2,290,000 $ 4,676,000 0 4,360,000 1. Compute gross profit or loss to be recognized as a result of this contract for each of the three years. Curtiss concludes that the contract does not qualify for revenue recognition over time. 2. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute gross profit or loss to be recognized in each of the three years. 3. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute the amount to be shown in the balance sheet at the end of 2024 and 2025 as either cost in excess of billings or billings in excess of costs. Complete this question by entering your answers in the tabs below. Req 1 and 2 Req 3 1. Compute gross profit or loss to be recognized as a result of this contract for each of the three years. Curtiss concludes that the contract does not qualify for revenue recognition over time. 2. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute gross profit or loss to be recognized in each of the three years. Note: Leave no cells blank - be certain to enter "0" wherever required. Loss amounts should be indicated with a minus sign. Show less▲ Req 2 Gross Profit (Loss) Recognized ("Over Time") Req 1 Gross Profit (Loss) Recognized Year ("Upon Completion") 2024 $ 0 2025 2026 Total project profit (loss) $ 0 $ < Req 1 and 2 0 Req 3 >
Assuming Curtiss recognizes revenue over time according to percentage of completion, compute the amount to be shown in
the balance sheet at the end of 2024 and 2025 as either cost in excess of billings or billings in excess of costs.
Balance Sheet (Partial)
Current assets:
Current liabilities:
2024
2025
< Req 1 and 2
Req 3 >
Transcribed Image Text:Assuming Curtiss recognizes revenue over time according to percentage of completion, compute the amount to be shown in the balance sheet at the end of 2024 and 2025 as either cost in excess of billings or billings in excess of costs. Balance Sheet (Partial) Current assets: Current liabilities: 2024 2025 < Req 1 and 2 Req 3 >
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Intermediate Accounting: Reporting And Analysis
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning