Question
I need the answer quickly
![In the following table there are seven tasks, labeled a through g. Some tasks can be done concurrently (a and b)
while others cannot be done until their predecessor task is complete (c and d cannot begin until a is complete).
Additionally, each task has three time estimates: the optimistic time estimate (O), the most likely or normal time
estimate (M), and the pessimistic time estimate (P). The expected time (TE) is estimated.
Create Gantt chart and estimate critical path
Time estimates
Expected time
(TE)
Activity
Predecessor
Opt. (0)
Normal (M)
Pess. (P)
a
2
4
6.
4
b
3
9.
5
a
4
7
5
d
a
4
10
6.
e
b, c
4
5
7
f
d
3
8.
4
g
3
8.
e
Note:
- you can neglect time estimated and calculate only Expected time
- all times in days](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F24f9394a-a341-4b09-b7b0-01726537c0e6%2Fd0a2d24b-d265-41ee-b358-4429587ab4ca%2Fgu6xdpkd_processed.jpeg&w=3840&q=75)
Transcribed Image Text:In the following table there are seven tasks, labeled a through g. Some tasks can be done concurrently (a and b)
while others cannot be done until their predecessor task is complete (c and d cannot begin until a is complete).
Additionally, each task has three time estimates: the optimistic time estimate (O), the most likely or normal time
estimate (M), and the pessimistic time estimate (P). The expected time (TE) is estimated.
Create Gantt chart and estimate critical path
Time estimates
Expected time
(TE)
Activity
Predecessor
Opt. (0)
Normal (M)
Pess. (P)
a
2
4
6.
4
b
3
9.
5
a
4
7
5
d
a
4
10
6.
e
b, c
4
5
7
f
d
3
8.
4
g
3
8.
e
Note:
- you can neglect time estimated and calculate only Expected time
- all times in days
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps with 2 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Recommended textbooks for you
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
![Business in Action](https://www.bartleby.com/isbn_cover_images/9780135198100/9780135198100_smallCoverImage.gif)
![Purchasing and Supply Chain Management](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
![Production and Operations Analysis, Seventh Editi…](https://www.bartleby.com/isbn_cover_images/9781478623069/9781478623069_smallCoverImage.gif)
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.