Construction of an embankment needs 400,000 yd3 of fill. The fill should be compacted to at least 88% of the standard Proctor maximum dry density obtained in the lab, which is gammad_d,max = 128 pcf, but the contractor plans to exceed that by 2% to ensure passing quality control. The fill may be obtained from two companies (A and B) with the following profiles. Company A Distance from borrow pit to embankment: 25 miles Cost of haul ($/yd3-mile): 0.50 Cost of fill material ($/yd3): 1.50 Borrow soil moisture content: 16% Specific gravity of solids: 2.70 Degree of saturation: 70% Company B Distance from borrow pit to embankment: 30 miles Cost of haul ($/yd3-mile): 0.40 Cost of fill material ($/yd3): 1.40 Borrow soil moisture content: 18% Specific gravity of solids: 2.65 Degree of saturation: 58% The total cost of haulage by company A (million $) The total cost of haulage by company B (million $) The relative compaction, CR, should account for the contractor's plan to exceed the minimum CR stipulated in the contract. For the volume Vs needed for the fill, V= (1+e) Vs needs to be excavated and hauled, charging the project at its own rate.
Construction of an embankment needs 400,000 yd3 of fill. The fill should be compacted to at least 88% of the standard Proctor maximum dry density obtained in the lab, which is gammad_d,max = 128 pcf, but the contractor plans to exceed that by 2% to ensure passing quality control. The fill may be obtained from two companies (A and B) with the following profiles. Company A Distance from borrow pit to embankment: 25 miles Cost of haul ($/yd3-mile): 0.50 Cost of fill material ($/yd3): 1.50 Borrow soil moisture content: 16% Specific gravity of solids: 2.70 Degree of saturation: 70% Company B Distance from borrow pit to embankment: 30 miles Cost of haul ($/yd3-mile): 0.40 Cost of fill material ($/yd3): 1.40 Borrow soil moisture content: 18% Specific gravity of solids: 2.65 Degree of saturation: 58% The total cost of haulage by company A (million $) The total cost of haulage by company B (million $) The relative compaction, CR, should account for the contractor's plan to exceed the minimum CR stipulated in the contract. For the volume Vs needed for the fill, V= (1+e) Vs needs to be excavated and hauled, charging the project at its own rate.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
Related questions
Question
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 2 images
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning