Construction Corporation has a contract to construct a building for $10,950,000. The building is controlled by the customer throughout the term of the contract. Total costs to complete the building were originally estimated at $8,850,000. Construction commenced on 4 February 20×5. Actual costs were in line with estimated costs for 20×5 and 20×6. In 20×7, actual costs exceeded estimated costs by $150,000.Total construction costs incurred in each year were as follows:20X5: $2,700,00020X6: $4,500,00020X7: $1,800,000Progress billings based on the amount of work completed were collected each year. Star Construction uses the percentage-of-completion method. The percentage-of-completion is based on costs incurred compared with estimated total costs of the project.Company also billed the client and collected the following paymentsYear Billings Payments Received20X5: $2,300,000 $2,100,00020X6: $4,900,000 $4,700,00020X7: $3,750,000 $4,150,000Required: Calculate Net income for the construction project for each of the three years:a) Completed contract method?20X5: $______________ 20X6: $__________________ 20X7____________________. b) Percentage-of-completion method? (basis: estimated costs to complete)20X5: $______________ 20X6: $__________________ 20X7____________________.
Construction Corporation has a contract to construct a building for $10,950,000. The building is controlled by the customer throughout the term of the contract. Total costs to complete the building were originally estimated at $8,850,000. Construction commenced on 4 February 20×5. Actual costs were in line with estimated costs for 20×5 and 20×6. In 20×7, actual costs exceeded estimated costs by $150,000.
Total construction costs incurred in each year were as follows:
20X5: $2,700,000
20X6: $4,500,000
20X7: $1,800,000
Progress billings based on the amount of work completed were collected each year. Star Construction uses the percentage-of-completion method. The percentage-of-completion is based on costs incurred compared with estimated total costs of the project.
Company also billed the client and collected the following payments
Year Billings Payments Received
20X5: $2,300,000 $2,100,000
20X6: $4,900,000 $4,700,000
20X7: $3,750,000 $4,150,000
Required: Calculate Net income for the construction project for each of the three years:
a) Completed contract method?
20X5: $______________ 20X6: $__________________ 20X7____________________.
b) Percentage-of-completion method? (basis: estimated costs to complete)
20X5: $______________ 20X6: $__________________ 20X7____________________.
![](/static/compass_v2/shared-icons/check-mark.png)
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 3 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
![FINANCIAL ACCOUNTING](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781259964947/9781259964947_smallCoverImage.jpg)
![Accounting](https://www.bartleby.com/isbn_cover_images/9781337272094/9781337272094_smallCoverImage.gif)
![Accounting Information Systems](https://www.bartleby.com/isbn_cover_images/9781337619202/9781337619202_smallCoverImage.gif)
![FINANCIAL ACCOUNTING](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781259964947/9781259964947_smallCoverImage.jpg)
![Accounting](https://www.bartleby.com/isbn_cover_images/9781337272094/9781337272094_smallCoverImage.gif)
![Accounting Information Systems](https://www.bartleby.com/isbn_cover_images/9781337619202/9781337619202_smallCoverImage.gif)
![Horngren's Cost Accounting: A Managerial Emphasis…](https://www.bartleby.com/isbn_cover_images/9780134475585/9780134475585_smallCoverImage.gif)
![Intermediate Accounting](https://www.bartleby.com/isbn_cover_images/9781259722660/9781259722660_smallCoverImage.gif)
![Financial and Managerial Accounting](https://www.bartleby.com/isbn_cover_images/9781259726705/9781259726705_smallCoverImage.gif)