Complete the table, solve for Completion date, Identify the Critical Path, Show Solutions and Network Diagram: Hint: Expected time = (a+4m+b)/6 Preceeding TimeEstimate Early Early Late Late Activity Activity Optimistic (a) Most Likely (m) Pessimestic (b) Expected Time Start Finish Start Finish A 4 5 12 B 1 1.5 5 A 2 3 4 D A 3 4 11 E A 2 3 4 F 1.5 2 2.5 G D 1.5 3 4.5 H В, Е 2.5 3.5 7.5 H 1.5 2 2.5 F, G, I 1 2 3
Complete the table, solve for Completion date, Identify the Critical Path, Show Solutions and Network Diagram: Hint: Expected time = (a+4m+b)/6 Preceeding TimeEstimate Early Early Late Late Activity Activity Optimistic (a) Most Likely (m) Pessimestic (b) Expected Time Start Finish Start Finish A 4 5 12 B 1 1.5 5 A 2 3 4 D A 3 4 11 E A 2 3 4 F 1.5 2 2.5 G D 1.5 3 4.5 H В, Е 2.5 3.5 7.5 H 1.5 2 2.5 F, G, I 1 2 3
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
Related questions
Question
![Complete the table, solve for Completion date, Identify the Critical Path, Show
Solutions and Network Diagram:
Hint: Expected time = (a+4m+b)/6
Preceeding
TimeEsti mate
Early
Early
Late
Late
Activity
Activity
Optimistic (a) Most Likely (m)|Pessimestic (b) Expected Time
Start
Finish
Start
Finish
A
4
5
12
В
1.5
A
2
3
4
D
A
3
4
11
A
2
4
F
1.5
2
2.5
G
D
1.5
3
4.5
H
В, Е
2.5
3.5
7.5
H
1.5
2
2.5
F, G, I
1
2
3](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F0078aef9-5099-41a3-83b4-19767afb2949%2F476a0334-bd99-4c62-8e0e-52b976ff14c6%2Fvysje2k_processed.png&w=3840&q=75)
Transcribed Image Text:Complete the table, solve for Completion date, Identify the Critical Path, Show
Solutions and Network Diagram:
Hint: Expected time = (a+4m+b)/6
Preceeding
TimeEsti mate
Early
Early
Late
Late
Activity
Activity
Optimistic (a) Most Likely (m)|Pessimestic (b) Expected Time
Start
Finish
Start
Finish
A
4
5
12
В
1.5
A
2
3
4
D
A
3
4
11
A
2
4
F
1.5
2
2.5
G
D
1.5
3
4.5
H
В, Е
2.5
3.5
7.5
H
1.5
2
2.5
F, G, I
1
2
3
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps with 3 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
![Structural Analysis](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781337630931/9781337630931_smallCoverImage.jpg)
![Structural Analysis (10th Edition)](https://www.bartleby.com/isbn_cover_images/9780134610672/9780134610672_smallCoverImage.gif)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
![Principles of Foundation Engineering (MindTap Cou…](https://www.bartleby.com/isbn_cover_images/9781337705028/9781337705028_smallCoverImage.gif)
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
![Structural Analysis](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781337630931/9781337630931_smallCoverImage.jpg)
![Structural Analysis (10th Edition)](https://www.bartleby.com/isbn_cover_images/9780134610672/9780134610672_smallCoverImage.gif)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
![Principles of Foundation Engineering (MindTap Cou…](https://www.bartleby.com/isbn_cover_images/9781337705028/9781337705028_smallCoverImage.gif)
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
![Fundamentals of Structural Analysis](https://www.bartleby.com/isbn_cover_images/9780073398006/9780073398006_smallCoverImage.gif)
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
![Sustainable Energy](https://www.bartleby.com/isbn_cover_images/9781337551663/9781337551663_smallCoverImage.gif)
![Traffic and Highway Engineering](https://www.bartleby.com/isbn_cover_images/9781305156241/9781305156241_smallCoverImage.jpg)
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning