Using the CPM , draw the CPM diagram and find the critical path analysis. Activity Preceeding Activity Time (WEEKS) A NONE 4 B NONE 6 C A, B 7 D B 8 E B 5 F C 5 G D 7 H D, E 8 I F,G, H 4
Using the CPM , draw the CPM diagram and find the critical path analysis.
Activity Preceeding Activity Time (WEEKS)
A NONE 4
B NONE 6
C A, B 7
D B 8
E B 5
F C 5
G D 7
H D, E 8
I F,G, H 4