Calculate the ES, EF, LS, and LF times and the slack for each activity in the figure below, and identify the critical path for the project. Can the project be completed in 30 weeks? Assume that "Systems Analysis" actually finished at 8 weeks, "Design Input & Output" actually finished at 15 weeks, and "Design Database" actually finished at 19 weeks. Recalculate the expected project completion time. Which activities would you focus on to get the project back on schedule?
Calculate the ES, EF, LS, and LF times and the slack for each activity in the figure below, and identify the critical path for the project. Can the project be completed in 30 weeks? Assume that "Systems Analysis" actually finished at 8 weeks, "Design Input & Output" actually finished at 15 weeks, and "Design Database" actually finished at 19 weeks. Recalculate the expected project completion time. Which activities would you focus on to get the project back on schedule?
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
![Calculate the ES, EF, LS, and LF times and the slack for each activity in the figure below, and identify
the critical path for the project. Can the project be completed in 30 weeks? Assume that "Systems
Analysis" actually finished at 8 weeks, "Design Input & Output" actually finished at 15 weeks, and
"Design Database" actually finished at 19 weeks. Recalculate the expected project completion time.
Which activities would you focus on to get the project back on schedule?
Problem
Definition
1
System
Analysis
Design
Input &
Output
Design
Database
4
15
Develop
Input
Screens
Develop
Output
Reports
6
8
10
Develop
Database
8
Test
System
Implement
System
6 9
5
+](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F6d674fe9-a550-43ff-965c-c12854b5103b%2F2a52d301-45ae-403a-bb88-42424e8f8af5%2Fxvzb2up_processed.jpeg&w=3840&q=75)
Transcribed Image Text:Calculate the ES, EF, LS, and LF times and the slack for each activity in the figure below, and identify
the critical path for the project. Can the project be completed in 30 weeks? Assume that "Systems
Analysis" actually finished at 8 weeks, "Design Input & Output" actually finished at 15 weeks, and
"Design Database" actually finished at 19 weeks. Recalculate the expected project completion time.
Which activities would you focus on to get the project back on schedule?
Problem
Definition
1
System
Analysis
Design
Input &
Output
Design
Database
4
15
Develop
Input
Screens
Develop
Output
Reports
6
8
10
Develop
Database
8
Test
System
Implement
System
6 9
5
+
![KEY:
Activity
Number
Earliest
Start
Earliest
Finish
Activity
Description
Latest
Start
Latest
Finish
Person
Responsible
Estimated
Duration](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F6d674fe9-a550-43ff-965c-c12854b5103b%2F2a52d301-45ae-403a-bb88-42424e8f8af5%2F45e3mat_processed.jpeg&w=3840&q=75)
Transcribed Image Text:KEY:
Activity
Number
Earliest
Start
Earliest
Finish
Activity
Description
Latest
Start
Latest
Finish
Person
Responsible
Estimated
Duration
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 4 steps with 4 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Recommended textbooks for you
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
![Business in Action](https://www.bartleby.com/isbn_cover_images/9780135198100/9780135198100_smallCoverImage.gif)
![Purchasing and Supply Chain Management](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
![Production and Operations Analysis, Seventh Editi…](https://www.bartleby.com/isbn_cover_images/9781478623069/9781478623069_smallCoverImage.gif)
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.