Calculate the ES, EF, LS, and LF times and the slack for each activity in the figure below, and identify the critical path for the project. Can the project be completed in 30 weeks? Assume that "Systems Analysis" actually finished at 8 weeks, "Design Input & Output" actually finished at 15 weeks, and "Design Database" actually finished at 19 weeks. Recalculate the expected project completion time. Which activities would you focus on to get the project back on schedule?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Calculate the ES, EF, LS, and LF times and the slack for each activity in the figure below, and identify
the critical path for the project. Can the project be completed in 30 weeks? Assume that "Systems
Analysis" actually finished at 8 weeks, "Design Input & Output" actually finished at 15 weeks, and
"Design Database" actually finished at 19 weeks. Recalculate the expected project completion time.
Which activities would you focus on to get the project back on schedule?
Problem
Definition
1
System
Analysis
Design
Input &
Output
Design
Database
4
15
Develop
Input
Screens
Develop
Output
Reports
6
8
10
Develop
Database
8
Test
System
Implement
System
6 9
5
+
Transcribed Image Text:Calculate the ES, EF, LS, and LF times and the slack for each activity in the figure below, and identify the critical path for the project. Can the project be completed in 30 weeks? Assume that "Systems Analysis" actually finished at 8 weeks, "Design Input & Output" actually finished at 15 weeks, and "Design Database" actually finished at 19 weeks. Recalculate the expected project completion time. Which activities would you focus on to get the project back on schedule? Problem Definition 1 System Analysis Design Input & Output Design Database 4 15 Develop Input Screens Develop Output Reports 6 8 10 Develop Database 8 Test System Implement System 6 9 5 +
KEY:
Activity
Number
Earliest
Start
Earliest
Finish
Activity
Description
Latest
Start
Latest
Finish
Person
Responsible
Estimated
Duration
Transcribed Image Text:KEY: Activity Number Earliest Start Earliest Finish Activity Description Latest Start Latest Finish Person Responsible Estimated Duration
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 4 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.