Calculate NPV for each project. Do not round intermediate calculations. Round your answers to the nearest cent. Project M: $ Project N: $ Calculate IRR for each project. Do not round intermediate calculations. Round your answers to two decimal places. Project M: % Project N: % Calculate MIRR for each project. Do not round intermediate calculations. Round your answers to two decimal places. Project M: % Project N: % Calculate payback for each project. Do not round intermediate calculations. Round your answers to two decimal places. Project M: years Project N: years Calculate discounted payback for each project. Do not round intermediate calculations. Round your answers to two decimal places. Project M: years Project N: years Assuming the projects are independent, which one(s) would you recommend? If the projects are mutually exclusive, which would you recommend?
A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including
0 | 1 | 2 | 3 | 4 | 5 |
Project M | -$27,000 | $9,000 | $9,000 | $9,000 | $9,000 | $9,000 |
Project N | -$81,000 | $25,200 | $25,200 | $25,200 | $25,200 | $25,200 |
-
Calculate NPV for each project. Do not round intermediate calculations. Round your answers to the nearest cent.
Project M: $
Project N: $
Calculate
IRR for each project. Do not round intermediate calculations. Round your answers to two decimal places.Project M: %
Project N: %
Calculate MIRR for each project. Do not round intermediate calculations. Round your answers to two decimal places.
Project M: %
Project N: %
Calculate payback for each project. Do not round intermediate calculations. Round your answers to two decimal places.
Project M: years
Project N: years
Calculate discounted payback for each project. Do not round intermediate calculations. Round your answers to two decimal places.
Project M: years
Project N: years
-
Assuming the projects are independent, which one(s) would you recommend?
-
If the projects are mutually exclusive, which would you recommend?
-
Notice that the projects have the same cash flow timing pattern. Why is there a conflict between NPV and IRR?