c) If the firm operates 8 hours per day, 6 days per week, the weekly capacity of the work cell with the second machine at workstation 2 is 24 units (enter your response as a whole number).

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
The Pullman​ Mfg., Inc.​ three-station work cell illustrated in the figure below has two machines at station 1 in parallel.​ (The product needs to go through only one of the two machines before proceeding to station​ 2.)
 
 
SEE PICTURE 
 
Answer C
 
 
**Manufacturing System Evaluation**

The diagram represents a manufacturing process with the following stations:

1. **Station 1**:
   - Machine A: 20 minutes per unit.
   - Machine B: 20 minutes per unit.

2. **Station 2**: 12 minutes per unit.

3. **Station 3**: 8 minutes per unit.

**Scenario**:
The manager, Ms. Hartley, wants to evaluate adding a parallel machine at Station 2.

**Results**:

a) **Throughput Time**: The throughput time of the new work cell is 40 minutes.

b) **Bottleneck Time**: The bottleneck time of the new work cell is 10 minutes per unit.

c) **Weekly Capacity**: If the firm operates 8 hours per day, 6 days per week, the weekly capacity of the work cell with the second machine at Station 2 is 24 units.
Transcribed Image Text:**Manufacturing System Evaluation** The diagram represents a manufacturing process with the following stations: 1. **Station 1**: - Machine A: 20 minutes per unit. - Machine B: 20 minutes per unit. 2. **Station 2**: 12 minutes per unit. 3. **Station 3**: 8 minutes per unit. **Scenario**: The manager, Ms. Hartley, wants to evaluate adding a parallel machine at Station 2. **Results**: a) **Throughput Time**: The throughput time of the new work cell is 40 minutes. b) **Bottleneck Time**: The bottleneck time of the new work cell is 10 minutes per unit. c) **Weekly Capacity**: If the firm operates 8 hours per day, 6 days per week, the weekly capacity of the work cell with the second machine at Station 2 is 24 units.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.