b. The Eastern Solutions Company Limited (ESCL) has tendered for, and won a contract to design and build a computerized flood-warning system in Trinidad and Tobago. Consider the activities, durations, and predecessor relationships to roll out this project, in the following network, shown in Table 2 (below). Draw the network and answer the questions that follow. Table 2. ESCL Computerized Flood-Warning System Project Activity Description Immediate Predecessor(s) Time Optimistic (Weeks) Most Likely (Weeks) Pessimistic (Weeks) A --- 2 7 12 B --- 1 3 11 C A 3 6 9 D B 5 8 13 E D 2 5 8 F E 4 9 14 G C 3 4 5 H D, G 3 5 7 I D 6 7 14 (ii) Identify the Critical Path or Paths in this project.
b. The Eastern Solutions Company Limited (ESCL) has tendered for, and won a contract to design and build a computerized flood-warning system in Trinidad and Tobago. Consider the activities, durations, and predecessor relationships to roll out this project, in the following network, shown in Table 2 (below). Draw the network and answer the questions that follow. Table 2. ESCL Computerized Flood-Warning System Project Activity Description Immediate Predecessor(s) Time Optimistic (Weeks) Most Likely (Weeks) Pessimistic (Weeks) A --- 2 7 12 B --- 1 3 11 C A 3 6 9 D B 5 8 13 E D 2 5 8 F E 4 9 14 G C 3 4 5 H D, G 3 5 7 I D 6 7 14 (ii) Identify the Critical Path or Paths in this project.
Purchasing and Supply Chain Management
6th Edition
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
ChapterC: Cases
Section: Chapter Questions
Problem 1.8A
Related questions
Question
b. The Eastern Solutions Company Limited (ESCL) has tendered for, and won a contract to
design and build a computerized flood-warning system in Trinidad and Tobago. Consider the
activities, durations, and predecessor relationships to roll out this project, in the following
network, shown in Table 2 (below). Draw the network and answer the questions that follow.
Table 2. ESCL Computerized Flood-Warning System Project
Activity
Description
Immediate
Predecessor(s)
Time
Optimistic
(Weeks)
Most Likely
(Weeks)
Pessimistic
(Weeks)
A --- 2 7 12
B --- 1 3 11
C A 3 6 9
D B 5 8 13
E D 2 5 8
F E 4 9 14
G C 3 4 5
H D, G 3 5 7
I D 6 7 14
(ii) Identify the Critical Path or Paths in this project.
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 3 steps with 4 images
Recommended textbooks for you
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning