b) The critical activities for the leadership training program development project are c) The project length for the leadership training program development project = d) Slack time for each of the activities is: Activity A Slack Time с B-D-E-G C-F-G
Roger Ginde is developing a program in
Activity |
Immediate Predecessor(s) |
Time (days) |
A |
− |
4 |
B |
− |
6 |
C |
− |
1 |
D |
B |
10 |
E |
A, D |
5 |
F |
C |
5 |
G |
E, F |
8 |
This exercise contains only parts b, c, and d.
Part 2
b) The critical activities for the leadership training program development project are
▼
B - D - E - G
C - F - G
A - E - G
.
Part 3
c) The project length for the leadership training program development project =
enter your response here
days.
Part 4
d) Slack time for each of the activities is:
|
|
|
|
Part 5
|
|
Part 6
|
|
Part 7
|
|
Part 8
|
|
Part 9
|
|
Part 10
|
|