A time study was conducted on a job that contains four elements. The observed times and performance ratings for six cycles are shown in the following table. Performance Element Rating 1 95% 1234 2 3 4 90 125 110 1 0.46 1.46 0.81 1.06 Element 1 2 3 4 Click here for the Excel Data File OBSERVATIONS (minutes per cycle) 2 3 4 5 6 0.51 0.41 0.41 0.41 0.41 1.41 1.41 1.41 1.46 1.46 0.81 0.71 0.76 0.81 0.76 1.11 1.06 1.11 1.11 1.16 a. Determine the average cycle time for each element. (Round your answers to 3 decimal places.) Average cycle

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
A time study was conducted on a job that contains four elements. The observed times and performance ratings for six cycles are
shown in the following table.
Element
1
2
3
4
Performance
Rating
95%
90
125
110
1
0.46
1.46
0.81
1.06
Element
1
2
3
4
Click here for the Excel Data File
Element
1
2
OBSERVATIONS (minutes per cycle)
Average cycle
2
0.51
1.46
0.81
1.11
a. Determine the average cycle time for each element. (Round your answers to 3 decimal places.)
Normal time
3
0.41
1.41
0.71
1.06
4
5
6
0.41 0.41 0.41
1.41 1.41 1.46
0.76 0.81 0.76
1.11 1.11 1.16
b. Find the normal time for each element. (Round your answers to 3 decimal places.)
< Prev
3 of 7
Next >
Transcribed Image Text:A time study was conducted on a job that contains four elements. The observed times and performance ratings for six cycles are shown in the following table. Element 1 2 3 4 Performance Rating 95% 90 125 110 1 0.46 1.46 0.81 1.06 Element 1 2 3 4 Click here for the Excel Data File Element 1 2 OBSERVATIONS (minutes per cycle) Average cycle 2 0.51 1.46 0.81 1.11 a. Determine the average cycle time for each element. (Round your answers to 3 decimal places.) Normal time 3 0.41 1.41 0.71 1.06 4 5 6 0.41 0.41 0.41 1.41 1.41 1.46 0.76 0.81 0.76 1.11 1.11 1.16 b. Find the normal time for each element. (Round your answers to 3 decimal places.) < Prev 3 of 7 Next >
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.