An electric utility is considering a new power plant in northern Arizona. Power from the plant would be sold in the Phoenix area, where it is badly needed. Because the firm has received a permit, the plant would be legal; but it would cause some air pollution. The company could spend an additional $40 million at Year 0 to mitigate the environmental problem, but it would not be required to do so. The plant without mitigation would require an initial outlay of $240.20 million, and the expected cash Inflows would be $80 million per year for 5 years. If the firm does invest in mitigation, the annual inflows would be $84.06 million. Unemployment in the area where the plant would be built is high, and the plant would provide about 350 good jobs. The risk adjusted WACC is 19%. a. Calculate the NPV and IRR with mitigation. Enter your answer for NPV in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative values, if any, should be indicated by a minus sign. Do not round intermediate calculations. Round your answers to two decimal places. NPV: $ IRR: % million Calculate the NPV and IRR without mitigation. Enter your answer for NPV in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative values, if any, should be indicated by a minus sign. Do not round intermediate calculations. Round your answers to two decimal places. NPV: $ IRR: % million b. How should the environmental effects be dealt with when evaluating this project? I. The environmental effects should be treated as a remote possibility and should only be considered at the time in which they actually occur. II. The environmental effects if not mitigated would result in additional cash flows. Therefore, since the plant is legal without mitigation, there are no benefits to performing a "no mitigation" analysis. III. The environmental effects should be ignored since the plant is legal without mitigation. IV. The environmental effects should be treated as a sunk cost and therefore ignored. V. If the utility mitigates for the environmental effects, the project is not acceptable. However, before the company chooses to do the project without mitigation, it needs to make sure that any costs of "ill will" for not mitigating for the environmental effects have been considered in the original analysis. -Select- c. Should this project be undertaken? 1. The project should be undertaken only if they do not mitigate for the environmental effects. However, they have to make sure that they've done the analysis properly to avoid any "ill will" and additional "costs" that might result from undertaking the project without concern for the environmental Impacts. II. The project should be undertaken only under the "mitigation" assumption. III. The project should be undertaken since the IRR is positive under both the "mitigation" and "no mitigation" assumptions. IV. The project should be undertaken since the NPV is positive under both the "mitigation" and "no mitigation" assumptions. V. Even when no mitigation is considered the project has a negative NPV, so it should not be undertaken. -Select- ▼
An electric utility is considering a new power plant in northern Arizona. Power from the plant would be sold in the Phoenix area, where it is badly needed. Because the firm has received a permit, the plant would be legal; but it would cause some air pollution. The company could spend an additional $40 million at Year 0 to mitigate the environmental problem, but it would not be required to do so. The plant without mitigation would require an initial outlay of $240.20 million, and the expected cash Inflows would be $80 million per year for 5 years. If the firm does invest in mitigation, the annual inflows would be $84.06 million. Unemployment in the area where the plant would be built is high, and the plant would provide about 350 good jobs. The risk adjusted WACC is 19%. a. Calculate the NPV and IRR with mitigation. Enter your answer for NPV in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative values, if any, should be indicated by a minus sign. Do not round intermediate calculations. Round your answers to two decimal places. NPV: $ IRR: % million Calculate the NPV and IRR without mitigation. Enter your answer for NPV in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative values, if any, should be indicated by a minus sign. Do not round intermediate calculations. Round your answers to two decimal places. NPV: $ IRR: % million b. How should the environmental effects be dealt with when evaluating this project? I. The environmental effects should be treated as a remote possibility and should only be considered at the time in which they actually occur. II. The environmental effects if not mitigated would result in additional cash flows. Therefore, since the plant is legal without mitigation, there are no benefits to performing a "no mitigation" analysis. III. The environmental effects should be ignored since the plant is legal without mitigation. IV. The environmental effects should be treated as a sunk cost and therefore ignored. V. If the utility mitigates for the environmental effects, the project is not acceptable. However, before the company chooses to do the project without mitigation, it needs to make sure that any costs of "ill will" for not mitigating for the environmental effects have been considered in the original analysis. -Select- c. Should this project be undertaken? 1. The project should be undertaken only if they do not mitigate for the environmental effects. However, they have to make sure that they've done the analysis properly to avoid any "ill will" and additional "costs" that might result from undertaking the project without concern for the environmental Impacts. II. The project should be undertaken only under the "mitigation" assumption. III. The project should be undertaken since the IRR is positive under both the "mitigation" and "no mitigation" assumptions. IV. The project should be undertaken since the NPV is positive under both the "mitigation" and "no mitigation" assumptions. V. Even when no mitigation is considered the project has a negative NPV, so it should not be undertaken. -Select- ▼
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
Related questions
Question
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
Recommended textbooks for you
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education