alculate the EAC for both conveyor belt systems. (Negative amounts should be indicated by a minus sign. Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) EAC System A $ System B $ Which conveyor belt system should the firm choose? System B System A
Lang Industrial Systems Company (LISC) is trying to decide between two different conveyor belt systems. System A costs $260,000, has a four-year life, and requires $80,000 in pretax annual operating costs. System B costs $366,000, has a six-year life, and requires $74,000 in pretax annual operating costs. Suppose LISC always needs a conveyor belt system; when one wears out, it must be replaced. Assume the tax rate is 30 percent and the discount rate is 9 percent. |
Calculate the EAC for both conveyor belt systems. (Negative amounts should be indicated by a minus sign. Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) |
EAC | |
System A | $ |
System B | $ |
Which conveyor belt system should the firm choose? |
|
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 1 images