Q: Month Sales (000) Unites Feb 19 Mar 18 Apr 15 May 20 Jun 18 Jul 22 Aug 20 Forecast September sales…
A: Ans) This is weighted moving average problem. Formula: Forecast for September = 0.6*August Demand +…
Q: In an analyzation of the auto industry in the US using Porter's Five Forces (including the level of…
A: Introduction: Porter five- forces model: A strategic model devised by Michael Porter is most widely…
Q: 1) Max Z = x₁ + 3x2 s.t. 2x1 + 4x2 ≤ 14 6x1 + 2x2 ≤ 12 Xi≥0 The coefficients of the variables in the…
A: The objective function given is Max Z=x1+3x2 The objective function in a linear program refers to…
Q: How much do you believe the efficiency of the company's reverse logistics may benefit from better…
A: Logistics in simple terms is nothing but the movement of goods from point to another. This consists…
Q: What is the expected profit if 1,600 chairs are made?
A: Given data: Sales price = 15000/1000 = $15 per unitVC = 6000/1000 = $6 per unitFixed Costs = $4000
Q: 0.5 A 0.7 B % Station 1 2 3 0.5 Tasks B,A,C,D E,F G, H,I Total 0.1 D 59 LL F G 0.4 (W) The cycle…
A: Formulae used: Assembly Line efficiency = Task TimeCycle time×No.of station×100 Ideal time = Cycle…
Q: In general, when a consultant's fee proposal and the sponsor's independent fee estimate are within…
A: Post development of a detailed scope of services, satisfying the independent fee estimate (IFE), a…
Q: What is the short-term retail sales forecast for 1 to 3 years? What is the mid-term retail sales…
A: A forecast of future sales revenue is called a sales forecast. Most of the time, historical data,…
Q: 7. At what stage in the international product life cycle does a country usually import foreign…
A: An abstract representation of how a corporation develops over time and across national boundaries is…
Q: has 10 items. These items are stored in a stockroom. No safety stock is planned for these items. The…
A: Ans) Number of Items = 10 Inventory accuracy = 95% = 0.95 probability of successfully finding…
Q: One of the risks of Lean production systems is; a. Increasing productivity b. Absence of buffers,…
A: The goal of the management strategy known as lean manufacturing is to eliminate waste while…
Q: WhatYouNeed is an online retailer with operations in Northern Indiana. Their network includes five…
A: Waste is a major blocker in revenue generation for all the firms be it goods or services. Reducing…
Q: 4) Max Z = 4x1 + 8x2 s.t. 2x1 + 4x2 < 14 6x1 + 2x2 ≤ 12 Xi ≥0 Problem 4 should be graphed first.…
A: Given data is Max Z=4x1+8x2 Subject to constraints: 1.) 2x1+4x2≤142.) 6x1+2x2≤12xi≥0
Q: How can IIoT influence the operation and geographical scope in manufacturing SMEs?
A: For those who are certainly not familiar with the technology or the acronyms, who may need help…
Q: The Activity on node diagram in Fig 15.1 was prepared at the beginning of a software update project.…
A: 1. During forward pass in case of more than two preceding activities the early start will be…
Q: Solve the primal problem by the simplex method. Construct the dual for this primal problem. Find the…
A: Linear programming is a mathematical technique that is also used in operations management…
Q: What is the importance of Quality by Design in Pharmacy
A: Quality by design commonly written as QbD describes a pharmaceutical development approach that helps…
Q: Amazon Go was made possible by technologies such as computer vision, sensor fusion, and deep…
A: Since you have posted multiple questions, we will solve the first question for you as per our…
Q: A large insurance company maintains a central computing system that contains a variety of…
A: Given data: Arrival rate (λ)=35 call per hour Service rate (μ)= 19 calls per hour
Q: The project information of the project Automated Warehouse Order Picking System is presented as…
A: A network diagram related to the project is which shows the set sequence of the task that is done to…
Q: A flow shop is characterized by the: Few-standard product variety Many, unique set-ups Low…
A: In a flow shop, the production procedure adheres to a predetermined linear framework, and this…
Q: Was Joly overpaid? What factors probably led to this pay package?
A: 1. Joly wasn't overpaid since the average executive's cash pay, given the importance of Best Buy to…
Q: The UCC treats merchants differently from common, inexperienced sellers and buyers. How does the UCC…
A: All business transactions throughout the United States are governed & administered by the…
Q: 1. If your supplier becomes more profitable, Group of answer choices : A. Unless there are…
A: When a certain industry is not a large consumer for the suppliers, the profitability of the…
Q: idual ones, with no direct cost, to major multi-million- pound ones. This assessment tests the…
A: Project failure can be caused by a variety of factors, most of which can be prevented with…
Q: ess
A: (a) True.
Q: The upper and lower specification limits for a component are 5.20, and 5.30 ounces, respectively.…
A: Given, LSL = 5.2 USL = 5.3 Standard deviation = 0.05 Average = 5.24
Q: Draw a fishbone for postal service
A: Fishbone diagram: Fishbone diagrams are generally used in the manufacturing or…
Q: Kelly-Lambing, Inc., a builder of government contracted small ships, has a steady work force of 10…
A: Given, First unit takes 6100 hours Learning rate = 75% Learning coefficient b = Log(0.75)/Log(2) =…
Q: Kelly-Lambing, Inc., a builder of government contracted small ships, has a steady work force of 10…
A: Learning curve formula to compute the time taken for the first unit Y(x) = Kxn Here x is the unit…
Q: Which of the following is NOT true about crashing a project? O Never shorten an activity that is not…
A: A method of compressing the timetable is project crashing. It's most frequently employed when a…
Q: The company is considering whether or not they should drill the land. The cost of drilling is…
A: 1. EMV for drilling = (0.5 X 0 + 0.3 X 10000000 + 0.2 X 30000000) - Cost incurred in drilling…
Q: Describe the various functions of purchase orders. Describes the steps to register a purchase order…
A: The buyer/customer creates a purchase order (PO) to specify the items they wish to purchase from the…
Q: How much do you believe the efficiency of the company's reverse logistics may benefit from better…
A: Reverse logistics refers to keeping track of your products' life cycles once they reach the final…
Q: a) the 10th transplant 10.40 hours (round your response to two decimal places). b) The cost of 10th…
A: Given: Learning curve rate = 75% Time for first transplant = 27 hrs Cost per hour of surgery = $5000…
Q: Temple Trucking Co. just hired Ed Rosenthal to verify daily invoices and accounts payable. He took 7…
A: Given, First day time T1 = 7 hour 42 minutes = 462 minutes Learning curve = 0.85 Learning…
Q: What 3 tools from organizational behaviour would you use to create a positive culture?
A: Any business's operations are focused on producing favorable outcomes and reaping the rewards. The…
Q: The Maytubig Water Company purifies drinking water in Luzon and Mindanao, which it plans to…
A: Find the Given details below: Transportation table Plant Wholesaler Tacloban Ilo-ilo Ormoc…
Q: A bike repair plant is trying to determine how long the average line for a repair process will be.…
A: Given, Arrival rate a = 13 / hour Waiting time in line Wq = 5 minutes Length of line Lq = ?
Q: QUESTION 17 Knowledge in form of experiences that resides into humans' minds and is difficult to be…
A: Understanding acquired via learning or experience is known as knowledge. Knowledge is the…
Q: your company is facing the situation in which the demand is stochastic but the lead time is known…
A: Inventory management is a wide concept under operations management. By just reading this term, it…
Q: The MRP Planning Horizon must be at least as long as the product lead time True False
A: Application for materials requirements planning (MRP) plans ahead for the production and purchasing…
Q: What are the products that typically result from the following project stages: Project Start-up;…
A: Project: Project is defined as “A project is an activity to meet the creation of a unique product or…
Q: As part of the final requirement for the course ES034- Engineering Management, class M8C1 is…
A: Given data is
Q: 4 tangible benefits the canal clearing project will bring to the people of Western Province where…
A: The Western Province's residents will see immediate advantages from the canal clearance project that…
Q: According to the open system characteristic of equifinality, which of Porter's generic strategies is…
A: Introduction Equifinality:- An open system has a characteristic of equifinality which states that…
Q: Mo5. Identify two threads of continuity and two aspects of discontinuity in Chinese women’s work…
A: The employee management in the company is very much important for an organization to be successful…
Q: Subject: Procurement & sourcing Q): Why do government set production quota, explain with example?
A: Ans) Government set production quota due to many reasons. If production quota is set High, it means…
Q: Suppose a state department of education develops a new tool for assessing teacher performance.…
A: ANSWER : 1. First compare parameters that you already know with the parameters obtained from the…
Q: Should Laura talk with Drew’s manager about the situation now? Why or why not?
A: A cross-functional initiative to enhance customer service in her organisation has invited Laura…
N5
17. Aggregate operations planners seek to match supply and demand at the minimum overall cost and: a) keeping inventories at a minimum. b) hiring when necessary. c) keeping inventories at a maximum. d) by staying within company policy.
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
- Detailed information about any logistic company and the product or service it provides. The location and structure. The owners and their goals.#3 - At Freeze Inc. the manufacturing of each air conditioning has a variable cost of $400 per unit and it takes place in a facility that has a monthly fixed cost of $200,000. a. If Freeze Inc. sells each unit at $1,200 how many units do they need to sell every month to break-even? b. What is the monthly revenue at the break-even point? с. What is the monthly variable cost at the break-even point? d. What is the total operating cost at the break-even point? e. If Freeze Inc. sells 1,000 units at $1,000 each on a given month, calculate the profit. acer3-2) The optimal quantity of the three products and resulting revenue for Taco Loco is: A) 28 beef, 80 cheese, and 39.27 beans for $147.27. B) 10.22 beef, 5.33 cheese, and 28.73 beans for $147.27. C) 1.45 Z, 8.36 Y, and 0 Z for $129.09. D) 14 Z, 13 Y, and 17 X for $9.81. 3-3) Taco Loco is unsure whether the amount of beef that their computer thinks is in inventory is correct. What is the range in values for beef inventory that would not affect the optimal product mix? A) 26 to 38.22 pounds B) 27.55 to 28.45 pounds C) 17.78 to 30 pounds D) 12.22 to 28 pounds
- Determine whether the following is a feasible sales and operations plan. Assume that the company has 56,000labor hours available during the next planning period time horizon. Product Units Demanded Standard Hours (in hours/unit) A 14,000 0.95 B 35,000 0.95 C 5,500 1.70 D 28,500 0.20 The total labor hours required by these four products for the next quarter is ______ (Enter your response as a whole number.)2.17 For the following data, calculate the number of workers required for level production and the resulting month-end inventories. Each worker can produce 14 units per day, and the desired ending inventory is 9000 units. Month Working Days Forecast Demand Planned Production Planned Inventory 11,500 1 2 3 4 Total 20 24 12 19 28,000 27,500 28,500 28,500A firm pursuing a strategy based on customization and variety will tend to structure and manage its supply chain to accommodate more _____________ than a firm pursuing a strategy based on low-cost and high-volume. a.Quality b.Variation c.Capacity d.Productivity e.Streamlined flow
- Shown below is a partially completed MPS record for hand drills. a. Develop the MPS record for the hand drills. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.) Item: Hand drills Quantity on Hand: 30 Forecast Customer orders (booked) Projected on-hand inventory MPS quantity MPS start 1 15 20 N 40 25 3 15 15 Week Available-to- promise (ATP) inventory b. A distributor of the hand drills places an order for 15 units. What is the appropriate shipping date for the entire order? The order should ship on week (Enter your response as an integer.) 4 20 20 Order Policy: 60 units Lead Time: 1 week 5 55 0 6 35 01. What factors should be considered when selecting the appropriate capacity cushion? Howdoes the choice of capacity cushion relate to other decisions in operations management?To other functional areas? 2. Capacity planning requires a demand forecast for an extended period of time into thefuture. What concerns would you have regarding an extended forecast as a capacityplanner?“How many dozen should I put in the proofer?” asked Elizabeth, the new baker at the Sands Cafeteria. Rami El‐Hussieny was the day shift operations manager, and, unfortunately, he did not know how to answer Elizabeth's question. What she wanted to know was simple enough: How many dozen rolls should be placed in the proofer in anticipation of the night's dinner business? The problem was that the frozen dinner roll dough used at the Sands Cafeteria needed to be proof for at least 2 hours prior to being baked for 15 minutes. If too many rolls were proofed, they would never be needed, but they would still have to be baked and made into bread dressing or even tossed out. If too few dozen were proofed and the night was busier than anticipated, they would run out of “Fresh Baked Rolls” (one of the restaurant's signature items), and Rami knew that the night manager would be really upset. It was a daily guess, and sometimes Rami missed the guess! He wondered if a prebaked roll with a shelf life…
- Which of the following is NOT a strategic operations management decision? Select one: a. maintenance b. quality c. layout design d. price and. InventoryThe question below is from the attached image of a video case file from Operations Management: Processes and Supply Chains (11th Edition) by Krajewski, L. J., Malhotra, M. K. & Ritzman, L. P. Attached a video case discussion from chapter 12. Question three is here below: 3. Regarding the design of the Washable Deluxe Painting Kit supply chain, Crayola must evaluate the strategy of next-shoring in Asia or retaining an existing network that involves the assembly of the kits in the U.S. Compare and contrast these two supply chain designs from perspective of the decision factors and pitfalls for outsourcing discussed in the textWhy is operations view of consumer centerd on order winners and qualifiers like price sensitivity, delivery lead times and demand peak size ?