Actual quantity of materials used Standard price per unit of material Material price variance at the point of usage Total material variance Standard rate of labor per hour Labor efficiency variance Total labor variance 1,800 unit P5.7 P1,260.0 P2,400.0 P16.0 P16,000.0 P64,000.0 41,000 hour P52,000.0 P37,000.0 600 hour Total standard labor hours Actual variable overhead Actual fixed overhead Actual hours related to variable costs Standard hours related to fixed overhead 650 hour Budgeted fixed overhead Total spending variance Total overhead efficiency variance Volume variance P35,000.0 P6,000.0 P4,000.0 P2,500.0
Actual quantity of materials used Standard price per unit of material Material price variance at the point of usage Total material variance Standard rate of labor per hour Labor efficiency variance Total labor variance 1,800 unit P5.7 P1,260.0 P2,400.0 P16.0 P16,000.0 P64,000.0 41,000 hour P52,000.0 P37,000.0 600 hour Total standard labor hours Actual variable overhead Actual fixed overhead Actual hours related to variable costs Standard hours related to fixed overhead 650 hour Budgeted fixed overhead Total spending variance Total overhead efficiency variance Volume variance P35,000.0 P6,000.0 P4,000.0 P2,500.0
Principles of Cost Accounting
17th Edition
ISBN:9781305087408
Author:Edward J. Vanderbeck, Maria R. Mitchell
Publisher:Edward J. Vanderbeck, Maria R. Mitchell
Chapter8: Standard Cost Accounting—materials, Labor, And Factory Overhead
Section: Chapter Questions
Problem 23E: (Appendix) Calculating factory overhead: three variances Using the data given in E8-17, calculate...
Related questions
Question
100%
Please refer to the Picture below. Kindly show the complete solution. Thank you so much.
![The following information was provided to you by Charice Standard Company:
Actual quantity of materials used
Standard price per unit of material
Material price variance at the point of
Total material variance
1,800 units
P5.70
P1,260.00 F
P2,400.00 F
usage
Standard rate of labor per hour
Labor efficiency variance
Total labor variance
P16.00
P16,000.00 F
P64,000.00 U
41,000 hours
P52,000.00
P37,000.00
Total standard labor hours
Actual variable overhead
Actual fixed overhead
Actual hours related to variable costs
600 hours
Standard hours related to fixed overhead
650 hours
Budgeted fixed overhead
Total spending variance
Total overhead efficiency variance
Volume variance
P35,000.00
P6,000.00 U
P4,000.00 F
P2,500.00 U
Compute for the following:
19. Actual price of materials per unit
20. Standard quantity of materials used
21. Material quantity variance
22. Actual labor rate per hour
23. Actual labor hours utilized
24. Labor rate variance
25
Standard wariahla ouarhegd rato](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Fbf9d123f-3502-4f82-bafa-c70533f555cd%2Fc35a6310-9d11-43e2-87f9-66f1c752abeb%2Fz9moi6m_processed.jpeg&w=3840&q=75)
Transcribed Image Text:The following information was provided to you by Charice Standard Company:
Actual quantity of materials used
Standard price per unit of material
Material price variance at the point of
Total material variance
1,800 units
P5.70
P1,260.00 F
P2,400.00 F
usage
Standard rate of labor per hour
Labor efficiency variance
Total labor variance
P16.00
P16,000.00 F
P64,000.00 U
41,000 hours
P52,000.00
P37,000.00
Total standard labor hours
Actual variable overhead
Actual fixed overhead
Actual hours related to variable costs
600 hours
Standard hours related to fixed overhead
650 hours
Budgeted fixed overhead
Total spending variance
Total overhead efficiency variance
Volume variance
P35,000.00
P6,000.00 U
P4,000.00 F
P2,500.00 U
Compute for the following:
19. Actual price of materials per unit
20. Standard quantity of materials used
21. Material quantity variance
22. Actual labor rate per hour
23. Actual labor hours utilized
24. Labor rate variance
25
Standard wariahla ouarhegd rato
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Recommended textbooks for you
![Principles of Cost Accounting](https://www.bartleby.com/isbn_cover_images/9781305087408/9781305087408_smallCoverImage.gif)
Principles of Cost Accounting
Accounting
ISBN:
9781305087408
Author:
Edward J. Vanderbeck, Maria R. Mitchell
Publisher:
Cengage Learning
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College
![Accounting (Text Only)](https://www.bartleby.com/isbn_cover_images/9781285743615/9781285743615_smallCoverImage.gif)
Accounting (Text Only)
Accounting
ISBN:
9781285743615
Author:
Carl Warren, James M. Reeve, Jonathan Duchac
Publisher:
Cengage Learning
![Principles of Cost Accounting](https://www.bartleby.com/isbn_cover_images/9781305087408/9781305087408_smallCoverImage.gif)
Principles of Cost Accounting
Accounting
ISBN:
9781305087408
Author:
Edward J. Vanderbeck, Maria R. Mitchell
Publisher:
Cengage Learning
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College
![Accounting (Text Only)](https://www.bartleby.com/isbn_cover_images/9781285743615/9781285743615_smallCoverImage.gif)
Accounting (Text Only)
Accounting
ISBN:
9781285743615
Author:
Carl Warren, James M. Reeve, Jonathan Duchac
Publisher:
Cengage Learning
![Financial & Managerial Accounting](https://www.bartleby.com/isbn_cover_images/9781337119207/9781337119207_smallCoverImage.gif)
Financial & Managerial Accounting
Accounting
ISBN:
9781337119207
Author:
Carl Warren, James M. Reeve, Jonathan Duchac
Publisher:
Cengage Learning