a. The minimum project duration. b. The Critical Path c. The total float for each activity. d. The free float for each activity.
Q: Up, Up, and Away is a producer of kites and wind socks. Relevant data on the bottleneck operation in…
A: Given data; No. of shifts 2 shifts Given table; No. of hrs per shift 8…
Q: Suppose the due date of the project is 24 months and expected time of completion is 28 months, while…
A: Let, td=24 months te =28 months Probability of completion = 90% Probability can be calculated by…
Q: A manufacturer of office furniture has recently received a number of inquiries about its interest in…
A:
Q: How does one establish a work breakdown structure? What is it? What equipment and materials are…
A: The work breakdown structure (WBS) is a hierarchical representation of the scope of work to be…
Q: Café Michigan's manager, Gary Stark, suspects that demand for mocha latte coffees depends on the…
A: From the above given information, let, y^ =estimated value of mocha latte cofees xi ="ith" price per…
Q: Suppose the LCL for a control chart is 2, the UCL is 10, and the CL is 6. Which of the following…
A: Given LCL = 2 UCL = 10
Q: A careful analysis of the cost of operating an automobile was conducted by accounting manager Dia…
A: A statistical method called regression links a dependent variable to one or more independent…
Q: explain the role of upstream strategic logistics (supply logistics) towards the success of the…
A: Upstream strategic logistics is the process of managing the distribution of goods from the point of…
Q: Use the Big M method, work through the simplex method step by step to solve the following problem.…
A: The Big M technique is a modified version of the simplex approach used in linear programming (LP),…
Q: Given the following data on the number of complaints from customers in the past few weeks. Week…
A: Linear trend line is of the form: Y= a+bx where a is the intercept, b is the slope, x is the…
Q: part b is to solve using excel solver
A: Decision Variables: Suppose-xA represents potential location A for the substationxB represents…
Q: A farmer has 300 acres of available land and $60,000 to spend. He wants to plant the combination of…
A: Given LP- Max Profit (W) = 180x1 + 60x2 + 90x3S.t. -400x1 + 160x2 + 280x3≤57000 (Cost…
Q: ABC company creates specialty shipping bags that they sell to pharmaceutical companies across the…
A: Given that the 10 bundles of material can produce 12000 bags.
Q: a) Consider the following binary integer programing (BIP) problem: Minimize z = 5x₁ + 6x₂ + 7x3 +…
A: The given LPP is as follows: Min Z = 5 x1 + 6 x2 + 7 x3 + 8 x4 + 9 x5 subject to…
Q: estimated times, the critical path is A-C-G-J-K d) The estimated time for the critical path is…
A: Expected time of activity: Te=(a+4m+b)/6 The variance of an activity: Variance=((b-a)/6)^2
Q: how to draw the graphical solution
A: Linear programming is a mathematical technique that is also used in operations management…
Q: Discuss the impact of strategic management in project implementation.
A: The strategic management of a company's resources is essential to achieving its goals and…
Q: Check which variable(s) should be in your answer.Milling constraint 0 =WRONG Enter inequalities…
A: Linear programming is a mathematical technique that is also used in operations management…
Q: a) The time Determine and also estimate: Activity A estimates. the find expected to 10 which of…
A:
Q: Question 3 [Redistribution policies aim to address the problem of economic inequality, but there is…
A: The objective of redistribution policies is to minimize economic and income inequality. This is…
Q: South African rapper, Cassper Nyovest, has launched a business venture manufacturing his very own…
A: Demand forecasting is the process of predicting future demand for products, services, and resources.…
Q: A company orders a product from an outside supplier. The annual demand for the product is 65,000…
A: An indicator of the appropriate order size to reduce expenses for the company is the economic order…
Q: South African rapper, Cassper Nyovest, has launched a business venture manufacturing his very own…
A: Just-in-time manufacturing, or JIT, is a production philosophy that strives for the elimination of…
Q: Discuss the main components that are likely to be included in the risk management system.
A: Risk management is an integral part of any management process because any company cannot neglect…
Q: Avery Collins Kinsley McDonnough Ross Shannon 2012 Total Sales by Agent January - June January…
A: Find the Given details below: Given details January February March April May June Avery $…
Q: Which statement is true? A. In the Service (Productt) Processs matrix, the degree of labor…
A: Service process matrix can be defined as a classification matrix of the service industry firms based…
Q: Why do you need a good WBS to use project management software? What other types of software can you…
A: A Good WBS could help us with many opportunities, and it would come with detailing all the major…
Q: rivers purchased $80 billion of ExxonMobil-produced gasoline during a recent year, with one-half…
A: GDP refers to Gross Domestic Product. GDP is defined as the standard measure of value added with…
Q: used to measure quality and cite the advantages and disadvantages of their utilization.
A: Employers may readily grasp and interpret information with the use of quality management systems,…
Q: To keep up with the volume of information transmitted between origin and destination points, use the…
A: Linear programming is a mathematical technique that is also used in operations management…
Q: ABC company creates specialty shipping bags that they sell to pharmaceutical companies across the…
A: Productivity is an important part of an organization's core activities. It is that concept that…
Q: Suppose the distances (in kilometers) that a pharmaceutical representative, Tracy Ross, travels…
A: Given data is
Q: In the following table the activities with their precedence sequence and expected time (days) are…
A: Network diagram of given data:
Q: 5. Consider the following problem = 2x₁ - x₂ + x3, Maximize Z = 3x₁ + x₂ + x3 ≤ 6 (resource 1) x₁ -…
A: Given Simplex Tableau-
Q: a. (**) Draw a precedence diagram for the tasks. Suppose the university needs to process 30…
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Q: Evaluate the essential components of a corporate strategy and how they are related in a project…
A: Corporate strategy is a well established long term plan which helps to describe and accomplish the…
Q: Describe the most important problems in risk management. How crucial is risk management to the…
A: Risk management can be broadly defined as the process of identification, evaluation, prevention and…
Q: Solve the transport problem by using the method of the potentials if the following initial…
A: Find the given details below: Transportation table Suppliers Consumers b1 b2 b3 b4 Supply…
Q: With the use of examples, explain to your colleagues in the buying department any (12) SIX criteria…
A: Supplier management is a process that is used to identify, select, and develop suppliers who can…
Q: would you recommend Techtonic use, and why?
A: Indeed, we would surely recommend Techtonic use for the following reasons. Organizations like…
Q: Q.2) Partially completed products arrive at a workstation in a manufacturing operation at a mean…
A: Average cost is the per unit cost of production which is calculated by dividing the total cost of…
Q: Please define the distinction between distribution and logistics. Are they the same task?
A: The term distribution and logistics are somewhat different. The differences between them with one…
Q: any, its suppliers, and oth
A: Supply chain management, which controls the flow of goods and services, includes all procedures used…
Q: Why it is important important to understand your break even point
A: Breakeven point is a quantity of item or total dollar which facilitate the total cost equal to total…
Q: Describe a normal probability distribution that can be used to approximate the demand distribution.…
A: Expected selling price = $24 Cost = $16 Salvage value = $5
Q: mid west university is installing a high speed intranet System. The following Netwerk shows a…
A: The shortest route problem helps to find the path that will have the minimum distance or cost or any…
Q: Slim-Down Manufacturing makes a line of nutritionally complete, weight-reduction beverages. One of…
A: Given data is Ingredient Calories from fat Total Calories Vitamin content Thickeners Cost…
Q: he number of plumbing repair jobs performed by Augur’s Plumbing Service during each month last year.…
A:
Q: Find the minimum value of the function z=2x+2y subject to the following constraints. x≤17 y≤16…
A: Linear programming is a mathematical technique for the optimization of resources, such as time and…
Q: First off, why is it so important for students, interns, and business owners to get familiar with…
A: According to the business lexicon, operations management is the design, execution, and control of…
Kindly give me ALL right solution according to the question.
Step by step
Solved in 4 steps with 4 images
- B/U pe Activity A B D 11. A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $4,000 per week for every week the project exceeds 37 weeks. What is the lowest total cost for completing this project? Predecessor Time 18 11 A A B C E D Normal A H 12 15 3 19 Asbe de ABC' AMBBC RACE AB 7 8 12 6 Normal Cost Crash Time Crash Cost $22,000 $32,000 $62,000 $18,000 $35,000 $8,000 $23,000 $32,000 $56,000 $12,000 5 $18,000 19 $22,000 $9,000 $15,000 $5,000 $13,000 $20,000 $45,000 2 5 4You are the project manager of the software installationproject in Table 7.12. You would like to find the minimum-costschedule for your project. There is a $1,000-per-week penaltyfor each week the project is delayed beyond week 25. In addi-tion, your project team determined that indirect project costsare $2,500 per week.a. What would be your target completion week?b. How much would you save in total project costs with yourschedule?How to Plan, direct and coordinate IT projects to ensure effectiveproject control including scope changes and project risks?
- Dave is the project manager for a construction project that is building agazebo. When the project first started, he met with the stakeholders to definethe scope. The sponsors mentioned that the gazebo is a really important partof their daughter’s wedding ceremony that was planned for 7 months fromthen. In fact, they said that if the gazebo couldn’t be completed in 7 months, itwouldn’t be worth it for them to even start the project. Dave wrote down the7-month deadline to put in his Project Scope Statement. In which section ofthe document did the deadline appear?”A. Project ConstraintsB. Project DeliverablesC. Project ObjectivesD. Project Assumptions Which of the following is a “hygiene factor” under Herzberg’s Motivation-Hygiene Theory?A. Recognition for excellent workB. Self-actualizationC. Clean clothingD. Good relations with coworkers and managersACTIVITY WK(S) PRECEDES CRASH COST/WEEK A(START $370 $120 $220 1 $140 F(END) 3 $400 Suppose that Rafay is only given 8 weeks (instead of 10) to complete the project. By how many weeks should each activity be crashed in order to meet the deadline? Assume that you can crash an activity down to 0 weeks duration. Activity Each Activity Should be Reduced BY (weeks) A O week(s) B1 week(s) C 2 week(s) E O week(s) F Oweek(s) What is the total crashing cost? $ nothing (Enter your response as a whole number.) PLEASE SHOW ME HOW TO GET THE CALUCLATION ON MY OWN SHOW YOUR STEPS i DO KNOW THAT CC-NC/NT-CT BUT I DONT KNOW WHAT FIGURES GOES WHERE AND WHY B с E 3 2 4 B,C E F Fon in OMGT 1013 x (1) Facebook - usl-tuguegarao.neolms.com/student take_quiz_assignment/display/23380965?part=14&r ODE 606 ÖMGT 1013 Item 14 of 78 Refer to the given information below for a particular project. Activity Immediate Predecessors Time (weeks) A None 2 BD 4. 3 E F Compute the slack time for activity D A. LL
- 2. Joe and Noël have just gotten engaged. As they are both business students, they thought they'd try to plan their wedding preparation as a project. Here's the WBS they've determined is necessary for a simple but elegant wedding. Assume all durations are deterministic. Although perhaps not realistic to real wedding planning, by using the standard calendar in Project Libre (use default working days in software). Task ID Task Name Duration Predecessor 1 Begin Wedding Planning (milestone) 0 days --- 2 Select Site&Date 3 wks 1 3 Hire Officiant 1 wk 2 4 Hire Caterers 2 wks 1 5 Pick Menu 4 days 4 6 Order Invitations 2 wks 2,5 7 Sent Invitations to Guests 1 wk 6 8 Collect RSVPs 6 wks 7 9 Tell Caterer headcount & Order food 1 wk 8 10 Shop for Wedding Gown 4 wks 1 11 Select Bridesmaids Dresses 4 wks 10 12 Bride goes on Diet 6 wks 10 13 Get Wedding Gown altered 2 wks 12 14 Get Bridemaids' Dresses altered 4 wks 11 15 Order Flowers 2 wks 11 16…O O D 40 4 22:31 photo_2021-02-2... O By using Bar chart planning method, find the following: - Total duration for the project activities shown below - The project completion date (assume the start date is 1/3/2012 Activity A В CDEF GHIJ Duration 8 28 4 6. 4 5 6 (days) Following C,DEFGH Activity * If the project shown above had a delay of (4 days after (13working days), what would its new delivery date be? 7. 5,ces Mailings Po V ates) EE E AL Review View Tell me $ Text Predictions: On 4 BIU 1. Evergreen Company wants to construct a new office building. The company has contracted a construction management contractor for this project. Given below are the details of a construction project. ✓ ✓ ✓ % Activity A 5 B C D ¶ E F — a) Construct the project network (AON) diagram for Evergreen Company and list all possible activity paths and their duration. b) Determine Evergreen Company's critical path(s). What is the duration of project competition? c) Determine the ES, EF, LS, LF, and floats for each activity. d) Construct a Gantt chart for Evergreen Company's project. AaBbCcDdEe Normal A STR 6 Predecessor(s) Duration (days) 1 2 A A B B, C E AaBbCcDdEe No Spacing !!! 3 2 1 1 & 7 E Do AaBbCcL AaBbCcDd AaBb AaBbCeDdE Heading 1. Heading 2 Title Subtitle * 00 8 I 9 Focus ( ) 0 Comm > St F
- 7. Contract requirements state that a project must be completed within 180 working days, or it will incur penalties for late completion. Analysis of the activity network reveals an expected project completion time of 145 working days with a project variance of 400. What is the probability that the project will be completed before the late-payment deadline? (select the closest answer) Select one: a. about 4% b. over 99% c. about 80% d. about 46% e. about 96%In the space provided below create the network diagram that shows the relationship (logic) of project activities shown below and then number each event. 1. In a given project activities "A, B and C are initial activities that may begin at the same time 2. -----"D" cannot begin until "A" is complete. 3. ----- "B" must be complete before E can begin. 4. ----- "F" cannot start until "C" is finished. 5. ----- "G" cannot begin until "B" is finished. 6. ----- "G" and "D" must be done before "H" can begin. 7. ----- "I" cannot begin until "B" is finished. 8. ----- "J" can begin only after "F" and "I" are complete. 9. ----- Once "E" is complete, "K" can begin. 10. ---- The project will be finished when "H" "J" and "K" are complete.The following precedence diagram reflects three time estimates for each activity. Determine: Use Table B1 and Table B2. 9-10-12 3 8 5-7-10 8-10-14 11-12-13 6 11 14-18-26 10.5-13-15.5 10 8-8-8 1 5-6-7 2 4 13-13-13 7 7-10-12 a. The expected completion time for each path and its variance. (Round intermediate calculations to 4 decimal places and final answers to 2 decimal places.) Path Mean Var. Std. Dev. 1-2-3-8-11 37.33 1-2-4-6-11 43.00 5.11 1-2-4-7-11 0.81 1-2-5-9-10-11 46.83 1.25 9-9-9 10-11-12 10-12-14