a. Determine the settlement of a clay layer
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
Related questions
Question
1. A soil has the following profile:
0 – 4 m ∂T = 18.25 kn/m3
very compact sand layer
4 – 10 m ∂T= 18.50 kn/m3
very compact sand, gravel
10 – 16 m ∂T = 17.98 kn/m3
clay layer
a. Determine the settlement of a clay layer if the structure to be built will increase the
soil pressure at the center of clay layer by 80 Kpa. Cc = 0.20, e = 1.15.
ans. 7.03
b. How long will it take for the 95% settlement to occur? Cv = 0.019 m2
/month?
ans. 39.47
c. How much settlement will occur in 6 months?
ans. 0.703
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps with 2 images

Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you


Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON

Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning


Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON

Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning

Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education


Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning