Question
100%
As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised
assembly operation to achieve an output of 250 units per 8-hour day. Task times and precedence relationships are as
follows:
Duration
Immediate
Task
(minutes)
Predecessor
a
0.5
|
b
0.4
a
0.5
0.3
es
e
1.8
d
f
1.9
е, f
Do each of the following:
a. Determine the number of followers for each task.
Number of tasks following task a
Number of tasks following task b
Number of tasks following task c
Number of tasks following task d
Number of tasks following task e
Number of tasks following task f
Number of tasks following task g
Transcribed Image Text:As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 250 units per 8-hour day. Task times and precedence relationships are as follows: Duration Immediate Task (minutes) Predecessor a 0.5 | b 0.4 a 0.5 0.3 es e 1.8 d f 1.9 е, f Do each of the following: a. Determine the number of followers for each task. Number of tasks following task a Number of tasks following task b Number of tasks following task c Number of tasks following task d Number of tasks following task e Number of tasks following task f Number of tasks following task g
b. Determine the minimum cycle time, the maximum cycle time, and the calculated cycle time. (Round all answers up to
one decimal point. For example, round 1.83 up to 1.9.)
Minimum cycle time
minutes per unit
Maximum cycle time
minutes per unit
Calculated cycle time
minutes per unit
es
c. Determine the minimum number of stations needed. (Use your rounded cycle time from Part b. Round up your
answer to a whole number. Note that rounding up to one decimal point may reduce output to slightly less than 250 and
this is fine.)
Minimum number of stations
Transcribed Image Text:b. Determine the minimum cycle time, the maximum cycle time, and the calculated cycle time. (Round all answers up to one decimal point. For example, round 1.83 up to 1.9.) Minimum cycle time minutes per unit Maximum cycle time minutes per unit Calculated cycle time minutes per unit es c. Determine the minimum number of stations needed. (Use your rounded cycle time from Part b. Round up your answer to a whole number. Note that rounding up to one decimal point may reduce output to slightly less than 250 and this is fine.) Minimum number of stations
Expert Solution
Step 1

Operations Management homework question answer, step 1, image 1

trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.