Titie A small project has 12 activities – N, P, Q, R, S, T, U, V, W, X, Y and Z. The relationship among these activities and the duration of these activities are given in the Table. Activity Duration (in weeks) Depends upon Q R 4 Q S 8. R U R,S 2. U W U T,V Y 1 W 3. X, Y The total float of the activity 'V' (in weeks, in 2jo integer) is

Engineering Fundamentals: An Introduction to Engineering (MindTap Course List)
5th Edition
ISBN:9781305084766
Author:Saeed Moaveni
Publisher:Saeed Moaveni
Chapter20: Engineering Economics
Section: Chapter Questions
Problem 40P
icon
Related questions
icon
Concept explainers
Question
Title
A small project has 12 activities – N, P, Q, R, S,
T, U, V, W, X, Y and Z. The relationship among
these activities and the duration of these activities
are given in the Table.
Activity Duration (in weeks) Depends upon
Q
4
P.
R
Q
S
8.
R
U
R,S
V
2
U
W
U
T,V
Y
1
W
3.
X, Y
The total float of the activity V' (in weeks, in
jo integer) is
Transcribed Image Text:Title A small project has 12 activities – N, P, Q, R, S, T, U, V, W, X, Y and Z. The relationship among these activities and the duration of these activities are given in the Table. Activity Duration (in weeks) Depends upon Q 4 P. R Q S 8. R U R,S V 2 U W U T,V Y 1 W 3. X, Y The total float of the activity V' (in weeks, in jo integer) is
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Budget estimating
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Engineering Fundamentals: An Introduction to Engi…
Engineering Fundamentals: An Introduction to Engi…
Civil Engineering
ISBN:
9781305084766
Author:
Saeed Moaveni
Publisher:
Cengage Learning