A regional municipality is studying a water supply plan for its tri-city and surrounding area to the end of year 2070. To satisfy the water demand, one suggestion is to construct a pipeline from a major lake some distance away. Construction would start at the beginning of 2030 and take five years at a cost of $30 million per year. The cost of maintenance and repairs starts after completion of construction and for the first year is $3 million, increasing by 2 percent per year thereafter. At an interest rate of 7 percent, what is the present worth of this project? Assume all cash flows take place at year-end. Consider the present to be the end of 2025/beginning of 2026. Assume there is no salvage value at the end of year 2070. Click the icon to view the table of compound interest factors for discrete compounding periods when i = 7%. The present worth of this project is $ million. (Round to two decimal places as needed.)

Advanced Engineering Mathematics
10th Edition
ISBN:9780470458365
Author:Erwin Kreyszig
Publisher:Erwin Kreyszig
Chapter2: Second-order Linear Odes
Section: Chapter Questions
Problem 1RQ
icon
Related questions
Question
A regional municipality is studying a water supply plan for its tri-city and surrounding area to the end of year 2070. To
satisfy the water demand, one suggestion is to construct a pipeline from a major lake some distance away. Construction
would start at the beginning of 2030 and take five years at a cost of $30 million per year. The cost of maintenance and
repairs starts after completion of construction and for the first year is $3 million, increasing by 2 percent per year
thereafter. At an interest rate of 7 percent, what is the present worth of this project? Assume all cash flows take place
at year-end. Consider the present to be the end of 2025/beginning of 2026. Assume there is no salvage value at the end
of year 2070.
Click the icon to view the table of compound interest factors for discrete compounding periods when i = 7%.
The present worth of this project is $
(Round to two decimal places as needed.)
million.
Transcribed Image Text:A regional municipality is studying a water supply plan for its tri-city and surrounding area to the end of year 2070. To satisfy the water demand, one suggestion is to construct a pipeline from a major lake some distance away. Construction would start at the beginning of 2030 and take five years at a cost of $30 million per year. The cost of maintenance and repairs starts after completion of construction and for the first year is $3 million, increasing by 2 percent per year thereafter. At an interest rate of 7 percent, what is the present worth of this project? Assume all cash flows take place at year-end. Consider the present to be the end of 2025/beginning of 2026. Assume there is no salvage value at the end of year 2070. Click the icon to view the table of compound interest factors for discrete compounding periods when i = 7%. The present worth of this project is $ (Round to two decimal places as needed.) million.
Expert Solution
Step 1: Evaluation of Present worth at year 2030

Present worth at year 2030equals C o n s t r u c t i o n space cos t open parentheses P divided by A comma i comma 5 close parentheses plus M a i n t e n a n c e space cos t open parentheses P divided by A comma g comma i comma 36 close parentheses open parentheses P divided by F comma i comma 5 close parentheses

equals $ 30 space open parentheses P divided by A comma 7 percent sign comma 5 close parentheses plus $ 3 space open parentheses P divided by A comma 2 percent sign comma 7 percent sign comma 36 close parentheses space open parentheses P divided by F comma 7 percent sign comma 5 close parentheses

equals $ 30 space cross times fraction numerator open parentheses 1 plus 0.07 close parentheses to the power of 5 minus 1 over denominator 0.07 open parentheses 1 plus 0.07 close parentheses to the power of 5 end fraction plus $ 3 cross times space fraction numerator 1 minus open parentheses fraction numerator 1 plus 0.02 over denominator 1 plus 0.07 end fraction close parentheses to the power of 36 over denominator 0.07 minus 0.02 end fraction cross times 1 over open parentheses 1 plus 0.07 close parentheses to the power of 5

equals $ 30 cross times 4.10020 plus $ 3 cross times 16.42875 cross times 0.7130

equals bold 158 bold. bold 147096

Hence, present worth at year 2030 will be $158.147096 million

steps

Step by step

Solved in 3 steps with 7 images

Blurred answer
Recommended textbooks for you
Advanced Engineering Mathematics
Advanced Engineering Mathematics
Advanced Math
ISBN:
9780470458365
Author:
Erwin Kreyszig
Publisher:
Wiley, John & Sons, Incorporated
Numerical Methods for Engineers
Numerical Methods for Engineers
Advanced Math
ISBN:
9780073397924
Author:
Steven C. Chapra Dr., Raymond P. Canale
Publisher:
McGraw-Hill Education
Introductory Mathematics for Engineering Applicat…
Introductory Mathematics for Engineering Applicat…
Advanced Math
ISBN:
9781118141809
Author:
Nathan Klingbeil
Publisher:
WILEY
Mathematics For Machine Technology
Mathematics For Machine Technology
Advanced Math
ISBN:
9781337798310
Author:
Peterson, John.
Publisher:
Cengage Learning,
Basic Technical Mathematics
Basic Technical Mathematics
Advanced Math
ISBN:
9780134437705
Author:
Washington
Publisher:
PEARSON
Topology
Topology
Advanced Math
ISBN:
9780134689517
Author:
Munkres, James R.
Publisher:
Pearson,