A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 64 percent complete. The planners were expecting to be only 53 percent through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that this would cost $1,423,000 and it was done for only $1,303,000. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,503,000 but was actually done for $9,003,000. The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,503,000. To date they have spent $5,003,000 on the superstructure. Calculate the schedule variance, schedule performance index, and cost performance index for the project to date. (Negative values should be indicated by a minus sign. Do not round your intermediate calculations or "variance" values. Round your "performance index" values to 3 decimal places.) Schedule variance Schedule performance index Cost performance index
A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 64 percent complete. The planners were expecting to be only 53 percent through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that this would cost $1,423,000 and it was done for only $1,303,000. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,503,000 but was actually done for $9,003,000. The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,503,000. To date they have spent $5,003,000 on the superstructure. Calculate the schedule variance, schedule performance index, and cost performance index for the project to date. (Negative values should be indicated by a minus sign. Do not round your intermediate calculations or "variance" values. Round your "performance index" values to 3 decimal places.) Schedule variance Schedule performance index Cost performance index
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
100%
Expert Solution
FORMULAS
I have arranged the given data in the form of a table:
Actual progress | 64% |
Planned Progress | 53% |
Budget for 1st activity | 1423000 |
Budget for 2nd activity | 10503000 |
Budget for 3rd activity | 8503000 |
Actual cost for 1st activity | 1303000 |
Actual cost for 2nd activity | 9003000 |
Actual cost for 3rd activity | 5003000 |
Now, Formulas are:
(A) Planned Value = Budget of Three activities Planned Progress
Earned Value = Budget of Three activities Actual Progress.
Schedule Variance = Planned Value - Earned Value
(B) Schedule Performance Index = Earned Value / Planned Value
(C) Actual Cost = Actual Cost of Three activities
Cost Performance Index = Earned Value / Actual Cost.
Trending now
This is a popular solution!
Step by step
Solved in 3 steps
Recommended textbooks for you
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.