A manufacturing system consists of 3 machines. Parts arrive following EXPO(5) distribution. Upon arrival, the parts will be send to the shops where they will be processed, each part will be transported individually (assume the parts move by themselves without the need of a resource) and the move time takes UNIF(2, 3) minutes. Once the parts arrive at the shop station the parts are distributed among the machines by selecting the machine with the shortest queue, if there are ties, then the tie breaker is the machine index (Machine 3 is prioritized over machine 2, and 1, and machine 2 is prioritized over machine 1). There is no maximum buffer capacity to be considered. Processing time for each machine is constant and is equal to 7 minutes. All three machines have failure modes; the machines have up times and down time as following: Machine 1 Up Time expo(140) min, Down Time UNIF(5,10) min, Machine 2 up time EXPO(100) min and down time UNIF(5, 15) + 5 min while for machine 3 up time EXPO(50) and down time UNIF(8,9). Do 20 replications of 200 hours and select the correct answers only: Source of the variability in this model is from the arrival process The maximum number waiting for each machine is less than 3. Machine 3 has the highest utilization of about 78% The max WIP is less than 20 parts. Machine 2 is failed about 7% of the time. Machine 3 is idle 7% of the time

Elements Of Electromagnetics
7th Edition
ISBN:9780190698614
Author:Sadiku, Matthew N. O.
Publisher:Sadiku, Matthew N. O.
ChapterMA: Math Assessment
Section: Chapter Questions
Problem 1.1MA
icon
Related questions
Question
A manufacturing system consists of 3 machines. Parts arrive following EXPO(5) distribution. Upon arrival, the parts will be send to
the shops where they will be processed, each part will be transported individually (assume the parts move by themselves without
the need of a resource) and the move time takes UNIF(2, 3) minutes. Once the parts arrive at the shop station the parts are
distributed among the machines by selecting the machine with the shortest queue, if there are ties, then the tie breaker is the
machine index (Machine 3 is prioritized over machine 2, and 1, and machine 2 is prioritized over machine 1). There is no maximum
buffer capacity to be considered. Processing time for each machine is constant and is equal to 7 minutes. All three machines have
failure modes; the machines have up times and down time as following: Machine 1 Up Time expo(140) min, Down Time UNIF(S, 10)
min, Machine 2 up time EXPO(100) min and down time UNIF(S, 15) + 5 min while for machine 3 up time EXPO(50) and down time
UNIF(8,9). Do 20 replications of 200 hours and select the correct answers only:
Source of the variability in this model is from the arrival process
B.
The maximum number waiting for each machine is less than 3.
Machine 3 has the highest utilization of about 78%
The max WIP is less than 20 parts.
Machine 2 is failed about 7% of the time.
Machine 3 is idle 7% of the time
Transcribed Image Text:A manufacturing system consists of 3 machines. Parts arrive following EXPO(5) distribution. Upon arrival, the parts will be send to the shops where they will be processed, each part will be transported individually (assume the parts move by themselves without the need of a resource) and the move time takes UNIF(2, 3) minutes. Once the parts arrive at the shop station the parts are distributed among the machines by selecting the machine with the shortest queue, if there are ties, then the tie breaker is the machine index (Machine 3 is prioritized over machine 2, and 1, and machine 2 is prioritized over machine 1). There is no maximum buffer capacity to be considered. Processing time for each machine is constant and is equal to 7 minutes. All three machines have failure modes; the machines have up times and down time as following: Machine 1 Up Time expo(140) min, Down Time UNIF(S, 10) min, Machine 2 up time EXPO(100) min and down time UNIF(S, 15) + 5 min while for machine 3 up time EXPO(50) and down time UNIF(8,9). Do 20 replications of 200 hours and select the correct answers only: Source of the variability in this model is from the arrival process B. The maximum number waiting for each machine is less than 3. Machine 3 has the highest utilization of about 78% The max WIP is less than 20 parts. Machine 2 is failed about 7% of the time. Machine 3 is idle 7% of the time
Expert Solution
steps

Step by step

Solved in 3 steps with 21 images

Blurred answer
Knowledge Booster
Project Management Techniques
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, mechanical-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Elements Of Electromagnetics
Elements Of Electromagnetics
Mechanical Engineering
ISBN:
9780190698614
Author:
Sadiku, Matthew N. O.
Publisher:
Oxford University Press
Mechanics of Materials (10th Edition)
Mechanics of Materials (10th Edition)
Mechanical Engineering
ISBN:
9780134319650
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Thermodynamics: An Engineering Approach
Thermodynamics: An Engineering Approach
Mechanical Engineering
ISBN:
9781259822674
Author:
Yunus A. Cengel Dr., Michael A. Boles
Publisher:
McGraw-Hill Education
Control Systems Engineering
Control Systems Engineering
Mechanical Engineering
ISBN:
9781118170519
Author:
Norman S. Nise
Publisher:
WILEY
Mechanics of Materials (MindTap Course List)
Mechanics of Materials (MindTap Course List)
Mechanical Engineering
ISBN:
9781337093347
Author:
Barry J. Goodno, James M. Gere
Publisher:
Cengage Learning
Engineering Mechanics: Statics
Engineering Mechanics: Statics
Mechanical Engineering
ISBN:
9781118807330
Author:
James L. Meriam, L. G. Kraige, J. N. Bolton
Publisher:
WILEY