A Hospital Management System Development Project has a budgeted cost of Rs. 11,900,000/-. The project is to be completed in 11 months. After 4 months, you have completed 24 percent of the project at a total expense of Rs. 1,475,000/-. You, as a Project Manager, needs to submit the monthly performance report to the Steering Committee. Based on EVM methodology, please identify the current progress of the Project. Find Budget at Completion (BAC), Actual Cost(AC), Planned Value (PV) and Earned Value (EV). Calculate the Project Health by finding values of Schedule Variance (SV), Schedule Performance Index (SPI), Cost Variance (CV) and Cost Performance Index (CPI). What these value shows? If the project continues at the current pace, what will be the true cost of the Project or Estimate at completion of the project. What actions, You would suggest or take as a Project Manager, to keep the budget and time under control.
A Hospital Management System Development Project has a budgeted cost of Rs. 11,900,000/-. The project is to be completed in 11 months. After 4 months, you have completed 24 percent of the project at a total expense of Rs. 1,475,000/-. You, as a Project Manager, needs to submit the monthly performance report to the Steering Committee. Based on EVM methodology, please identify the current progress of the Project. Find Budget at Completion (BAC), Actual Cost(AC), Planned Value (PV) and Earned Value (EV). Calculate the Project Health by finding values of Schedule Variance (SV), Schedule Performance Index (SPI), Cost Variance (CV) and Cost Performance Index (CPI). What these value shows? If the project continues at the current pace, what will be the true cost of the Project or Estimate at completion of the project. What actions, You would suggest or take as a Project Manager, to keep the budget and time under control.
Essentials Of Investments
11th Edition
ISBN:9781260013924
Author:Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Publisher:Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Chapter1: Investments: Background And Issues
Section: Chapter Questions
Problem 1PS
Related questions
Question
100%
A Hospital Management System Development Project has a budgeted cost of Rs. 11,900,000/-. The project is to be completed in 11 months. After 4 months, you have completed 24 percent of the project at a total expense of Rs. 1,475,000/-. You, as a Project Manager, needs to submit the monthly performance report to the Steering Committee. Based on EVM methodology, please identify the current progress of the Project.
- Find Budget at Completion (BAC), Actual Cost(AC), Planned Value (PV) and Earned Value (EV).
- Calculate the Project Health by finding values of Schedule Variance (SV), Schedule Performance Index (SPI), Cost Variance (CV) and Cost Performance Index (CPI). What these value shows?
- If the project continues at the current pace, what will be the true cost of the Project or Estimate at completion of the project.
- What actions, You would suggest or take as a Project Manager, to keep the budget and time under control.
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 3 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.Recommended textbooks for you
Essentials Of Investments
Finance
ISBN:
9781260013924
Author:
Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Publisher:
Mcgraw-hill Education,
Essentials Of Investments
Finance
ISBN:
9781260013924
Author:
Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Publisher:
Mcgraw-hill Education,
Foundations Of Finance
Finance
ISBN:
9780134897264
Author:
KEOWN, Arthur J., Martin, John D., PETTY, J. William
Publisher:
Pearson,
Fundamentals of Financial Management (MindTap Cou…
Finance
ISBN:
9781337395250
Author:
Eugene F. Brigham, Joel F. Houston
Publisher:
Cengage Learning
Corporate Finance (The Mcgraw-hill/Irwin Series i…
Finance
ISBN:
9780077861759
Author:
Stephen A. Ross Franco Modigliani Professor of Financial Economics Professor, Randolph W Westerfield Robert R. Dockson Deans Chair in Bus. Admin., Jeffrey Jaffe, Bradford D Jordan Professor
Publisher:
McGraw-Hill Education