A differential leveling loop began and closed on BM Tree (elevation 1314.08 ft). The plus sight and minus sight distances were kept approximately equal. Readings (in feet) lsted in the order taken are 3.04 (+S) on BM Tree, 4.76 (-S) and 2.36 (+S) on TP1, 3.05 (-S) and 6.63 (+S) on BM X, 3.64 (-S) and 235 (+S) on TP2, and 3 (-S) on BM Tree. Prepare, check, and adjust the notes. Part A What are the Plus and Minus adjustments? Express your answers, separated by a comma, to two decimal places. VO AE vec + Plus, Minus ft, ft Submit Request Answer Part B What are the misclosure and correction? Express your answers, separated by a comma, to three significant figures.

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
A differential leveling loop began and closed on BM Tree (elevation 1314.08 ft). The plus sight and minus sight distances were kept approximately equal. Readings (in feet) lsted in the
order taken are 3.04 (+S) on BM Tree, 4.76 (-S) and 2.36 (+S) on TP1, 3.05 (-S) and 6.63 (+S) on BM X, 3.64 (-S) and 235 (+S) on TP2, and 3 (-S) on BM Tree. Prepare, check, and
adjust the notes.
Part A
What are the Plus and Minus adjustments?
Express your answers, separated by a comma, to two decimal places.
Plus, Minus
ft, ft
Submit
Request Answer
Part B
What are the misciosure and correction?
Express your answers, separated by a comma, to three significant figures.
Transcribed Image Text:A differential leveling loop began and closed on BM Tree (elevation 1314.08 ft). The plus sight and minus sight distances were kept approximately equal. Readings (in feet) lsted in the order taken are 3.04 (+S) on BM Tree, 4.76 (-S) and 2.36 (+S) on TP1, 3.05 (-S) and 6.63 (+S) on BM X, 3.64 (-S) and 235 (+S) on TP2, and 3 (-S) on BM Tree. Prepare, check, and adjust the notes. Part A What are the Plus and Minus adjustments? Express your answers, separated by a comma, to two decimal places. Plus, Minus ft, ft Submit Request Answer Part B What are the misciosure and correction? Express your answers, separated by a comma, to three significant figures.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps

Blurred answer
Knowledge Booster
Unit conversion
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning