A contractor needs 440 m of nggregate base for a highway construction project. It wil be compacted to a dry unit wnight of 17 8 ANim Ths material is available in a stockpile at a local matenal supply yard at a water content of 8 5%, but is sold by the metric ton and not by cubic meters. I How many tons of oggregate should the contractor purchase? ( 2 A few weeks later, an intense rainstorm increased the water content of the stockpile to 14%. If the contractor orders the same quantity for an identical section of the highway, how many cubie meters of compacted aggregate base will he produce?

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
A contractor needs 440 m of nggregate base for a highway construction project. It will be compacted to a dry unit wnight of 17 8 KNim This malerial is availabie in a stockpile at a local
materal supply yard at a water content of 8 5%, but is sold by the motric ton and not by cutic metors.
I How many tons of oggregate should the contractor purchase?
2 A few weeks later, an intense rainstorm increased the water content of the stockpile to 14%, It the contractor orders the some quantity for an identical section of the highway.
how many cubic meters of compacted aggregate base will he produce?
Transcribed Image Text:A contractor needs 440 m of nggregate base for a highway construction project. It will be compacted to a dry unit wnight of 17 8 KNim This malerial is availabie in a stockpile at a local materal supply yard at a water content of 8 5%, but is sold by the motric ton and not by cutic metors. I How many tons of oggregate should the contractor purchase? 2 A few weeks later, an intense rainstorm increased the water content of the stockpile to 14%, It the contractor orders the some quantity for an identical section of the highway. how many cubic meters of compacted aggregate base will he produce?
Expert Solution
steps

Step by step

Solved in 2 steps with 3 images

Blurred answer
Knowledge Booster
Pricing excavation and backfill
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning