A construction project consists of 5 similar buildings, it is required to excavate 4200 m3 for foundations for each building. If the contractor has 5 excavators, and the productivity of each excavator is 17 m3/hour. assume that the number of working hours per day is 7 Note: put your answer up to 2 decimal places. Estimate the following requirements: Manhours for the excavation activity? Mandays for the excavation activity? Duration for the excavation activity? "days" If the number of excavators is increased by two, estimate the new Duration for the excavation activity? "days"

Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter10: Pricing Excavation And Backfill
Section: Chapter Questions
Problem 4RQ
icon
Related questions
icon
Concept explainers
Question

solve all the subparts correctly

A construction project consists of 5 similar buildings, it is
required to excavate 4200 m3 for foundations for each building.
If the contractor has 5 excavators, and the productivity of each
excavator is 17 m3/hour.
assume that the number of working hours per day is 7
Note: put your answer up to 2 decimal places.
Estimate the following requirements:
Manhours for the excavation activity?
Mandays for the excavation activity?
Duration for the excavation activity? "days"
If the number of excavators is increased by two, estimate the
new Duration for the excavation activity? "days"
Transcribed Image Text:A construction project consists of 5 similar buildings, it is required to excavate 4200 m3 for foundations for each building. If the contractor has 5 excavators, and the productivity of each excavator is 17 m3/hour. assume that the number of working hours per day is 7 Note: put your answer up to 2 decimal places. Estimate the following requirements: Manhours for the excavation activity? Mandays for the excavation activity? Duration for the excavation activity? "days" If the number of excavators is increased by two, estimate the new Duration for the excavation activity? "days"
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Electrical plans
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,