A construction project consists of 5 similar buildings, it is required to excavate 4200 m3 for foundations for each building. If the contractor has 5 excavators, and the productivity of each excavator is 17 m3/hour. assume that the number of working hours per day is 7 Note: put your answer up to 2 decimal places. Estimate the following requirements: Manhours for the excavation activity? Mandays for the excavation activity? Duration for the excavation activity? "days" If the number of excavators is increased by two, estimate the new Duration for the excavation activity? "days"
A construction project consists of 5 similar buildings, it is required to excavate 4200 m3 for foundations for each building. If the contractor has 5 excavators, and the productivity of each excavator is 17 m3/hour. assume that the number of working hours per day is 7 Note: put your answer up to 2 decimal places. Estimate the following requirements: Manhours for the excavation activity? Mandays for the excavation activity? Duration for the excavation activity? "days" If the number of excavators is increased by two, estimate the new Duration for the excavation activity? "days"
Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter10: Pricing Excavation And Backfill
Section: Chapter Questions
Problem 4RQ
Related questions
Question
solve all the subparts correctly
![A construction project consists of 5 similar buildings, it is
required to excavate 4200 m3 for foundations for each building.
If the contractor has 5 excavators, and the productivity of each
excavator is 17 m3/hour.
assume that the number of working hours per day is 7
Note: put your answer up to 2 decimal places.
Estimate the following requirements:
Manhours for the excavation activity?
Mandays for the excavation activity?
Duration for the excavation activity? "days"
If the number of excavators is increased by two, estimate the
new Duration for the excavation activity? "days"](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F02b01056-4eaf-479a-aa6c-2b4659d46d5e%2F7fd1582a-84c7-49aa-834a-e882c9188f8f%2Fkcehts_processed.jpeg&w=3840&q=75)
Transcribed Image Text:A construction project consists of 5 similar buildings, it is
required to excavate 4200 m3 for foundations for each building.
If the contractor has 5 excavators, and the productivity of each
excavator is 17 m3/hour.
assume that the number of working hours per day is 7
Note: put your answer up to 2 decimal places.
Estimate the following requirements:
Manhours for the excavation activity?
Mandays for the excavation activity?
Duration for the excavation activity? "days"
If the number of excavators is increased by two, estimate the
new Duration for the excavation activity? "days"
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
![Fundamentals Of Construction Estimating](https://www.bartleby.com/isbn_cover_images/9781337399395/9781337399395_smallCoverImage.gif)
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,
![Fundamentals Of Construction Estimating](https://www.bartleby.com/isbn_cover_images/9781337399395/9781337399395_smallCoverImage.gif)
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,