What would be the average completion time, if the Earliest Due Date First (EDD) rule were used to schedule the five orders? A. 4.2 hours B. 15.6 hours C. 13.6 hours D. 6 hours A bakery has five orders to be completed. Because of the nature and size of the orders, only one order can be baked at a time. The estimated baking time (in hours) and the hours until the order is due are shown below. Job 1 - 2 3 45 Processing time (hours) 7 9 3 5 2 Due Date (hours) 9 12 4 11 10 What would be the baking sequence, if the Critical Ratio First (CR) rule were used to schedule the five orders? Assume now is hour 0. A. 5, 3, 1, 4, 2 B. 2, 4, 1, 3, 5 C. 3, 1, 2, 4, 5 D. 1, 2, 3, 5, 4 What would be the average job lateness, if the Shortest Processing Time First (SPT) rule were used to schedule the five orders? A. 5.2 hours B. 15.6 hours C. D. 7 hours

EBK HEALTH ECONOMICS AND POLICY
7th Edition
ISBN:9781337668279
Author:Henderson
Publisher:Henderson
Chapter4: Economic Evaluation In Health Care
Section: Chapter Questions
Problem 7QAP
Question
What would be the average completion time, if the Earliest Due Date First (EDD) rule were used to schedule the five orders?
A. 4.2 hours
B. 15.6 hours
C. 13.6 hours
D. 6 hours
Transcribed Image Text:What would be the average completion time, if the Earliest Due Date First (EDD) rule were used to schedule the five orders? A. 4.2 hours B. 15.6 hours C. 13.6 hours D. 6 hours
A bakery has five orders to be completed. Because of the nature and size of the orders, only one order can be baked at a time. The estimated baking time (in hours) and the hours until the order is
due are shown below.
Job
1
- 2 3 45
Processing time (hours)
7
9
3
5
2
Due Date (hours)
9
12
4
11
10
What would be the baking sequence, if the Critical Ratio First (CR) rule were used to schedule the five orders? Assume now is hour 0.
A. 5, 3, 1, 4, 2
B. 2, 4, 1, 3, 5
C. 3, 1, 2, 4, 5
D. 1, 2, 3, 5, 4
What would be the average job lateness, if the Shortest Processing Time First (SPT) rule were used to schedule the five orders?
A. 5.2 hours
B. 15.6 hours
C.
D. 7 hours
Transcribed Image Text:A bakery has five orders to be completed. Because of the nature and size of the orders, only one order can be baked at a time. The estimated baking time (in hours) and the hours until the order is due are shown below. Job 1 - 2 3 45 Processing time (hours) 7 9 3 5 2 Due Date (hours) 9 12 4 11 10 What would be the baking sequence, if the Critical Ratio First (CR) rule were used to schedule the five orders? Assume now is hour 0. A. 5, 3, 1, 4, 2 B. 2, 4, 1, 3, 5 C. 3, 1, 2, 4, 5 D. 1, 2, 3, 5, 4 What would be the average job lateness, if the Shortest Processing Time First (SPT) rule were used to schedule the five orders? A. 5.2 hours B. 15.6 hours C. D. 7 hours
Expert Solution
steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Similar questions
Recommended textbooks for you
EBK HEALTH ECONOMICS AND POLICY
EBK HEALTH ECONOMICS AND POLICY
Economics
ISBN:
9781337668279
Author:
Henderson
Publisher:
YUZU
Managerial Economics: Applications, Strategies an…
Managerial Economics: Applications, Strategies an…
Economics
ISBN:
9781305506381
Author:
James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:
Cengage Learning
Managerial Economics: A Problem Solving Approach
Managerial Economics: A Problem Solving Approach
Economics
ISBN:
9781337106665
Author:
Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:
Cengage Learning
Economics (MindTap Course List)
Economics (MindTap Course List)
Economics
ISBN:
9781337617383
Author:
Roger A. Arnold
Publisher:
Cengage Learning
Microeconomics
Microeconomics
Economics
ISBN:
9781337617406
Author:
Roger A. Arnold
Publisher:
Cengage Learning
Microeconomic Theory
Microeconomic Theory
Economics
ISBN:
9781337517942
Author:
NICHOLSON
Publisher:
Cengage