8. You have signed a contract to build a garage for the Simpsons. You will re- ceive a $500 bonus for completing the project within 15 working days. The contract also contains a penalty clause in which you will lose $100 for each day the project takes longer than 15 working days. Draw a project network given the information below. Complete the forward and backward pass, compute the activity slack, and identify the critical path. Do you expect to receive a bonus or a penalty on this project? D ABCDEFGHI ID J Description Pour foundation Erect frame Roof Windows Doors Electrical Rough-in frame Door opener Paint Cleanup Predecessor None A (BBBB CES C, D, E, F E, F G, H I Time (days) 3 4 4 1 1 -32121 3 2

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Note:-

  • Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism.
  • Answer completely.
  • You will get up vote for sure.
8. You have signed a contract to build a garage for the Simpsons. You will re-
ceive a $500 bonus for completing the project within 15 working days. The
contract also contains a penalty clause in which you will lose $100 for each
day the project takes longer than 15 working days.
Draw a project network given the information below. Complete the forward
and backward pass, compute the activity slack, and identify the critical path.
Do you expect to receive a bonus or a penalty on this project?
D ABCDEFGHI
ID
Description
Pour foundation
Erect frame
Roof
Windows
Doors
Electrical
Rough-in frame
Door opener
Paint
Cleanup
Predecessor
None
A
B
BBBB JEG
C, D, E, F
E, F
G, H
I
Time
(days)
3
4
4
1
1
3
2
1
2
1
Transcribed Image Text:8. You have signed a contract to build a garage for the Simpsons. You will re- ceive a $500 bonus for completing the project within 15 working days. The contract also contains a penalty clause in which you will lose $100 for each day the project takes longer than 15 working days. Draw a project network given the information below. Complete the forward and backward pass, compute the activity slack, and identify the critical path. Do you expect to receive a bonus or a penalty on this project? D ABCDEFGHI ID Description Pour foundation Erect frame Roof Windows Doors Electrical Rough-in frame Door opener Paint Cleanup Predecessor None A B BBBB JEG C, D, E, F E, F G, H I Time (days) 3 4 4 1 1 3 2 1 2 1
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 8 steps with 6 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.