7. The local university has developed an eight-step process for screening the thousands of admissions applications it gets each year. The provost has decided that the best way to take a first cut at all these applications is by employing a line process. The following table shows the times and predecessors for the various tasks: TASK TIME (MINUTES) IMMEDIATE PREDECESSOR ABCDEFI G H 1.2 1 0.65 1.1 1.3 0.7 0.8 0.9 None A B B CDDF с D E, F, G a. (**) Draw a precedence diagram for the tasks. Suppose the university needs to process 30 applications an hour during the peak season. What is the takt time? What is the theoretical minimum number of workstations? b. (**) Develop workstation assignments by using the "largest eligible task" rule. c. (**) How many workstations does your solution require? What is the cycle time for the line? What is the idle time? What are the percent idle time and the effi- ciency delay?
7. The local university has developed an eight-step process for screening the thousands of admissions applications it gets each year. The provost has decided that the best way to take a first cut at all these applications is by employing a line process. The following table shows the times and predecessors for the various tasks: TASK TIME (MINUTES) IMMEDIATE PREDECESSOR ABCDEFI G H 1.2 1 0.65 1.1 1.3 0.7 0.8 0.9 None A B B CDDF с D E, F, G a. (**) Draw a precedence diagram for the tasks. Suppose the university needs to process 30 applications an hour during the peak season. What is the takt time? What is the theoretical minimum number of workstations? b. (**) Develop workstation assignments by using the "largest eligible task" rule. c. (**) How many workstations does your solution require? What is the cycle time for the line? What is the idle time? What are the percent idle time and the effi- ciency delay?
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
![7. The local university has developed an eight-step process
for screening the thousands of admissions applications it
gets each year. The provost has decided that the best way
to take a first cut at all these applications is by employing
a line process. The following table shows the times and
predecessors for the various tasks:
TASK TIME (MINUTES) IMMEDIATE PREDECESSOR
ABCDEF I
A
с
G
H
1.2
1
0.65
1.1
1.3
0.7
0.8
0.9
None
A
BBUD
с
D
E, F, G
a. (**) Draw a precedence diagram for the tasks. Suppose
the university needs to process 30 applications an hour
during the peak season. What is the takt time? What
is the theoretical minimum number of workstations?
b. (**) Develop workstation assignments by using the
"largest eligible task" rule.
c. (**) How many workstations does your solution
require? What is the cycle time for the line? What is the
idle time? What are the percent idle time and the effi-
ciency delay?
d. (***) In theory, what is the fastest cycle time possible,
given the tasks listed above? How many applications
per hour does this translate into?](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F054d0b4a-edca-48ba-9ebe-36c23e945d13%2F220b174c-acfa-4d20-a84d-f03d110e664f%2Fwiqg6jr_processed.png&w=3840&q=75)
Transcribed Image Text:7. The local university has developed an eight-step process
for screening the thousands of admissions applications it
gets each year. The provost has decided that the best way
to take a first cut at all these applications is by employing
a line process. The following table shows the times and
predecessors for the various tasks:
TASK TIME (MINUTES) IMMEDIATE PREDECESSOR
ABCDEF I
A
с
G
H
1.2
1
0.65
1.1
1.3
0.7
0.8
0.9
None
A
BBUD
с
D
E, F, G
a. (**) Draw a precedence diagram for the tasks. Suppose
the university needs to process 30 applications an hour
during the peak season. What is the takt time? What
is the theoretical minimum number of workstations?
b. (**) Develop workstation assignments by using the
"largest eligible task" rule.
c. (**) How many workstations does your solution
require? What is the cycle time for the line? What is the
idle time? What are the percent idle time and the effi-
ciency delay?
d. (***) In theory, what is the fastest cycle time possible,
given the tasks listed above? How many applications
per hour does this translate into?
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 5 steps with 7 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Recommended textbooks for you
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
![Business in Action](https://www.bartleby.com/isbn_cover_images/9780135198100/9780135198100_smallCoverImage.gif)
![Purchasing and Supply Chain Management](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
![Production and Operations Analysis, Seventh Editi…](https://www.bartleby.com/isbn_cover_images/9781478623069/9781478623069_smallCoverImage.gif)
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.