56. The following information is available for Mary Corp. Activity Pool Setups Quality Inspections Assembly (direct labor hour) What is the activity rate for setups? P5.09 Activity Base 50,000 120,000 400,000 Budgeted Amount 300,000 600,000 2,000,000 с. РО.75 d. P58.00 a. b. Рб.00 The activity rate for quality inspection is: c. Р6.00 d. P5.09 a. P5.29 b. P5.00

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question
Chapter 6: A Closer Look on Cost Accounting
The company makes 2,350 units of product X a year, requiring a total os
3.300 machine hours, 250 orders and 200 inspection hours per year. The
product's direct material cost is P201.50 and its direct labor cost in
P211.11 per unit. The product sells for P590 per unit. According to the
activity-based costing system, the gross margin for product X is?
423,087.50
b. 350,435.50
c. 416,890
d. None of the choice
a.
56.
The following information is available for Mary Corp.
Activity Pool
Setups
Quality Inspections
Assembly (direct labor hour)
What is the activity rate for setups?
Activity Base
50,000
120,000
400,000
Budgeted Amount
300,000
600,000
2,000,000
a. P5.09
c. РО.75
d. P58.00
b. Рб.00
The activity rate for quality inspection is:
с. Рб.00
d. P5.09
a. P5.29
b. P5.00
Transcribed Image Text:Chapter 6: A Closer Look on Cost Accounting The company makes 2,350 units of product X a year, requiring a total os 3.300 machine hours, 250 orders and 200 inspection hours per year. The product's direct material cost is P201.50 and its direct labor cost in P211.11 per unit. The product sells for P590 per unit. According to the activity-based costing system, the gross margin for product X is? 423,087.50 b. 350,435.50 c. 416,890 d. None of the choice a. 56. The following information is available for Mary Corp. Activity Pool Setups Quality Inspections Assembly (direct labor hour) What is the activity rate for setups? Activity Base 50,000 120,000 400,000 Budgeted Amount 300,000 600,000 2,000,000 a. P5.09 c. РО.75 d. P58.00 b. Рб.00 The activity rate for quality inspection is: с. Рб.00 d. P5.09 a. P5.29 b. P5.00
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Cost allocation
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education