5. Find the critical path and project completion time for the network given below:. Activity Immediate Predecessors Duration (Days) A B C D E F G H B A, D C E, F C 2 5 6 10 3689
Q: help meee
A: To solve both problems, use the Critical Path Method (CPM) to determine the earliest and latest…
Q: Isabel Briggs Myers was a pioneer in the study of personality types. The personality types are…
A: a) Probability X 0 1 2 3 4 P(X=x) 40/375=0.11 66/375=0.18 117/375=0.31 123/375=0.33…
Q: The Adelaide University Judo Club offers 2 fitness programs to enhance player fitness performance…
A: Note: Since you have posted a question with multiple sub-parts, we will provide the solution only to…
Q: Given below is the Activity list for a Project with the duration in weeks and Predecessor…
A: Step 1: Draw Activity - on - arrow diagram. This enables the project duration in weeks and…
Q: 12. You are creating a customer database for the Lehigh Valley IronPigs minor league baseball team.…
A:
Q: The following represent activities in Old Dominion's logistics project Activity Immediate…
A:
Q: Construct a table of inputs, computations, and output, then make a rule by utilizing the information…
A: The rule of the situation can be obtained by travelling through some computations. If it is…
Q: Rebecca's purchased a new android phone from Metro PCS. Her plan contains unlimited data and talk…
A: we have the given information that Rebecca purchased a new android phone Her plan consists of…
Q: H.W: Write a ladder program to control the cooling system. When the temperature degree Temp become…
A: Certainly! Here's an example of a ladder logic program that controls the cooling system based on the…
Q: A traveler is trying to determine the fastest way to travel from city A to city Z. The possible…
A: From the given graph and duration table:Starting point is A:From A to B duration is 36, and From A…
Q: 4. Match each graph with the statement that best describes it. a) Same initial value, different…
A: As per Bartleby guidelines for more than one questions asked only first should be answered. Please…
Q: For the following highway network system, determine the maximal flow in vehicles per hour. 1 3 2 2 5…
A: For the given network system, the derived paths are:Highway flow PathFlow capacity (1000 vehicles…
Q: It costs $40 to buy a telephone from the department store. Assume that I can keep a telephone for at…
A:
Q: Which of the following is not considered for formation of lagrangian function? O a. Equality…
A: Ans : Inequality constraints Option (b) true
Q: The graph of a function g is shown below. Find one value of x for which g(x)=4 and find g (2). = 4:…
A:
Q: 0 1 2 3 4 S 6 7 8 9 10 11 12 Year Determine the equation of the line of best fit. Question 19…
A:
Q: 2 Homework: Determine the critical path(s) for the following projects: E F C,D E 1 4 Activity…
A: # as per the guidelines we are entitled to solve one question at a time, please resubmit the other…
Q: The Phony TV company makes two different types of television sets, OLED and LED, which are assembled…
A: Consider the given: OLED model assembled per hour , when operated by line 1 =30 units. LED model…
Q: Consider the following transport network c. Find the maximum flow if if the indicated capacities are…
A: The objective of the question is to find the maximum flow in a transport network given certain…
Q: For each task build the relevant network diagram 2. Add the task durations for each activity 3.…
A: The network diagram is The Foreward pass method…
Q: 9. The table shows the minimum and maximum number of hours of sunlight in Dryden, Ontario, Hour of…
A:
Q: Construct index number of price from the following data by applying: 1)Fisher’s Ideal method…
A: Obtain the price index number of price from the following data by applying the Fisher’s Ideal…
Q: draw the scatter graph of this set of data X Y 10 1 20 3 40 4 50 5 30 2
A: The following data values are given. x y 10 1 20 3 40 4 50 5 30 2
Q: Inbox Unit 4 x Four Le X Americ X Studen x E EverFi x E Ventur x A…
A: White grape juice: 2 cups. Lime juice: 3/4 cup. Club soda: 4 cups. The ratio of mint leaves :…
Q: project are shown below. You must do the activity-on-arc network for this project to get credit for…
A:
Q: 1. Estimate the queue dissipation time, maximum queue length, and total delay, given: Time 3:00 -…
A: Given: To calculate the queue dissipation time, maximum queue length, and total delay
Q: 8. At a rock gym, the cost, c, to rent a pair of climbing shoes for h hours can be represented by…
A: Given equation is : c=3h
Q: Consider the facility location problem as shown on the figure below, where a network model of an…
A: We will chose minimum distanced paths from node 1 to node 9.
Q: The prices and the numbers of various items used by a construction company listed below: Item 2015…
A: Solution: The formula for the Fisher's Ideal Price Index is Fisher's Price Index Number =…
Q: Use North West corner rule to determine the starting solution, hence, an optimal solution to the…
A:
Q: 6. Consider a tax notch. The tax on total income I is given by S011 I 1000 90+0.21 Calculate the…
A:
Q: Find the below table which shows the task time. The Maximum output of the company is 240 bottles per…
A: Given the below table shows the task time. The maximum output of the company is 240 bottles per day…
Q: Equation y= 2 aput Output y 21 2. 1 4 2.
A: Explanation and solutions is given below....
Step by step
Solved in 5 steps with 3 images
- The following activities are part of a project to be scheduled using CPM: TIME (WEEKS) ACTIVITY A B с D E F G IMMEDIATE PREDECESSOR A A C 4 Number of weeks B&media:cm.png% D D E&media:cm.png8 F a. What is the critical path? O A-C-D-E-G O A-B-D-F-G OA-C-D-F-G A-B-E-G 3 q 8 3 5 b. How many weeks will it take to complete the project?Let us consider the case of LaRosa Machine Shop (LMS). LMS is studying where to locate its tool bin facility on the shop floor. The locations of the five production stations appear in the figure below. Y 5 3 Min 2 Fabrication 1 Station Paint Paint Subassembly 1 Fabrication (x, y) = Subassembly 1 Subassembly 2 Assembly Subassembly 2 2 1 4 1 3 X Y Demand 3 2.5 2 4 2 Assembly 5 4 4 11 25 12 6 16 X = horizontal location of the tool bin Y = vertical location of the tool bin 5 In an attempt to be fair to the workers in each of the production stations, management has decided to try to find the position of the tool bin that would minimize the sum of the distances from the tool bin to the five production stations. We define the following decision variables. 6 e We may measure the straight line distance from a station to the tool bin located at (X, Y) by using Euclidean (straight-line) distance. For example, the distance from fabrication located at the coordinates (1, 4) to the tool bin located…Only handwritten please. dony use excel.
- Table 1.1 (below) is a record of the travelling times of the time taken for ten (10) employees to deliver packages, to ten (10) of their distribution centres in Trinidad. These centres are located in Chaguanas (I), Arima (II), Sangre Grande (III), Princes Town (IV), Manzanilla (V), Rio Claro (VI), San Juan (VII), Point Fortin(VIII), San Fernando (IX) and Port of Spain (X). Worker Worker 1 Worker 2 Worker 3 Worker 4 Worker 5 Worker 6 Worker 7 Worker 8 Worker 9 Worker 10 I 26 30 29 26 29 27 25 30 25 25 II 40 45 30 32 37 37 42 41 41 40 Table 1.1 - Employee Travelling time (minutes) III 27 30 20 25 27 30 30 26 29 23 IV 35 32 32 30 31 30 35 28 36 30 V 39 35 30 36 35 36 30 30 40 38 Area VI 70 75 83 80 85 90 69 87 90 88 VII 30 30 34 29 27 30 34 28 30 32 VIII 75 79 80 75 76 69 66 67 78 68 IX 63 62 62 60 60 57 58 58 60 62 X 30 32 30 29 30 35 36 37 34 28The following table shows the price per share of Apple stock at the beginning of different months. Calculate the four-month weighted moving average for October 2021. Round your answer to the nearest cent. Month July 2021 August 2021 September 2021 October 2021 November 2021 December 2021 Apple Stock Price Simple Moving Average Weighted Moving Average $136.60 $146.36 $152.83 $141.90 $148.99 $167.48 ???How many slack variables exist(s) in the tableau to be created if we have: Show your solution. x + 2y ≤ 50 2x + 4y ≤ 100 x ≥ 0, y ≥ 0 a. 2 b. 4 c. 0 d. 3
- just wants the solution for part C no. iii2Example 11. Three type of shaping tools are produced in a factory using Act I, Activity II and Activity III. The duration in hours required to produce one bat tools in each of these activities are given in the following tables along with the cre selling prices each batch of tools and the minimum number of hours availahle each machine per week. Cost per Selling Price batch (Rs) (Rs) per bath Total Processing time (hrs.) per batch in type Activity I Activity II Activity III 8. 1 7 75 110 Q 2 5 60 90 R 4 3 3 75 130 Max, hours. 35 40 50 Formulate this problem as an LP model so as to maximise the total profit. CS Scanned with CamScanner
- ANSWER #4 npert The table shows the activities that need to be undertaken to complete a certain project as well as the respective times in weeks needed to complete the activities. Also shown are the predecessor activities or the activities that need to be completed before a particular activity may start.2. Determine the definition of the piece wise linear function shown in each of the graphs 3. Consider the following sets of data points. Decide in which cases you would chose a piecewise linear model to fit the data points. 4. For any part of question 3 that was suitable for meddling with piecewise linear function: a) draw this model “by eye” b) estimate the value of y when x=12 6. Consider the set of data points in the tableII) A firms production is represented by the following Cobb-Douglas function: Q = K13 L23. The rental rate, r, of capital is given by $16 and the price of labor is $4. a. For a given level of output, what should be the ratio of capital to labor in order to minimizecosts?b. How much capital and labor should be used to produce those 200 units?c. What is the minimum cost of producing 200 units?d. What is the additional cost of increasing output to 350 units in the short run and in the longrun?e. Does this production function exhibit increasing, decreasing, or constant returns to scale?Please answer based on the cost calculations in parts c and d.