project are shown below. You must do the activity-on-arc network for this project to get credit for the problem Determine the duration of the project and the critical path using the normal times. Show the critical path a. answer by entering letters separated by comas. i.e. B, D, F b. Determine the best (least cost) schedule for carrying out the project three (3) days ahead of normal schedule - Clearly specify the activities that must be crashed and the total cost of the project after every reduction in time. Job Normal Time | Crash Time | Normal Cost | Crash Cost Immediate (days) (days) Predecessors A 6 4 100 120 4 3 80 93 A C 5 4 95 110 7 7 115 115 A С, В В, D E 4 64 106 F 8. 6. 75 99

MATLAB: An Introduction with Applications
6th Edition
ISBN:9781119256830
Author:Amos Gilat
Publisher:Amos Gilat
Chapter1: Starting With Matlab
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
In planning a project to introduce a new product, the required activities, times and costs of activities in the
project are shown below. You must do the activity-on-arc network for this project to get credit for the problem
Determine the duration of the project and the critical path using the normal times. Show the critical path
а.
answer by entering letters separated by comas. i.e. B, D, F
b.
Determine the best (least cost) schedule for carrying out the project three (3) days ahead of normal schedule
- Clearly specify the activities that must be crashed and the total cost of the project after every reduction in time.
Job | Normal Time
(days)
Crash Time Normal Cost
(days)
4
Crash Cost Immediate
Predecessors
A
100
120
B
4
3
80
93
A
C
5
4
95
110
D
7
7
115
115
A
С, В
В, D
E
4
64
106
F
8
6.
75
99
Transcribed Image Text:In planning a project to introduce a new product, the required activities, times and costs of activities in the project are shown below. You must do the activity-on-arc network for this project to get credit for the problem Determine the duration of the project and the critical path using the normal times. Show the critical path а. answer by entering letters separated by comas. i.e. B, D, F b. Determine the best (least cost) schedule for carrying out the project three (3) days ahead of normal schedule - Clearly specify the activities that must be crashed and the total cost of the project after every reduction in time. Job | Normal Time (days) Crash Time Normal Cost (days) 4 Crash Cost Immediate Predecessors A 100 120 B 4 3 80 93 A C 5 4 95 110 D 7 7 115 115 A С, В В, D E 4 64 106 F 8 6. 75 99
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
Recommended textbooks for you
MATLAB: An Introduction with Applications
MATLAB: An Introduction with Applications
Statistics
ISBN:
9781119256830
Author:
Amos Gilat
Publisher:
John Wiley & Sons Inc
Probability and Statistics for Engineering and th…
Probability and Statistics for Engineering and th…
Statistics
ISBN:
9781305251809
Author:
Jay L. Devore
Publisher:
Cengage Learning
Statistics for The Behavioral Sciences (MindTap C…
Statistics for The Behavioral Sciences (MindTap C…
Statistics
ISBN:
9781305504912
Author:
Frederick J Gravetter, Larry B. Wallnau
Publisher:
Cengage Learning
Elementary Statistics: Picturing the World (7th E…
Elementary Statistics: Picturing the World (7th E…
Statistics
ISBN:
9780134683416
Author:
Ron Larson, Betsy Farber
Publisher:
PEARSON
The Basic Practice of Statistics
The Basic Practice of Statistics
Statistics
ISBN:
9781319042578
Author:
David S. Moore, William I. Notz, Michael A. Fligner
Publisher:
W. H. Freeman
Introduction to the Practice of Statistics
Introduction to the Practice of Statistics
Statistics
ISBN:
9781319013387
Author:
David S. Moore, George P. McCabe, Bruce A. Craig
Publisher:
W. H. Freeman