5. A contractor is getting soil fill from a 300 ft x 200 ft borrow pit. The soil will be excavated to a depth of 3 ft. The swell factor of the soil is 20% and the specific weight of the soil after excavation will be 115 lb/ft3. A single truck will be used to transport all the soil volume to a dump site. The truck's maximum capacity per load is the lesser of 12 yd3 or 15 tons. How many loads will be required to transport the soil fill to the dump?

Principles of Foundation Engineering (MindTap Course List)
9th Edition
ISBN:9781337705028
Author:Braja M. Das, Nagaratnam Sivakugan
Publisher:Braja M. Das, Nagaratnam Sivakugan
Chapter5: Soil Improvement And Ground Modification
Section: Chapter Questions
Problem 5.13P
icon
Related questions
Question

5. A contractor is getting soil fill from a 300 ft x 200 ft borrow pit. The soil will be excavated to a depth of 3 ft. The swell factor of the soil is 20% and the specific weight of the soil after excavation will be 115 lb/ft3. A single truck will be used to transport all the soil volume to a dump site. The truck's maximum capacity per load is the lesser of 12 yd3 or 15 tons. How many loads will be required to transport the soil fill to the dump?

Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning